problem 1: The project manager will have a number of issues to consider in construction site organization and management. Describe.
problem 2: Set out the procedures included in project registration and numbering.
problem 3: Describe the steps that require to be taken to make sure the effective conduct of project meetings.
problem 4: Describe the aim and content of a project variation order. Describe your answer with an illustration of an order.
problem 5: Describe what a project closure document is. Describe your answer with an illustration.
problem 6: How can subcontractors are used to help with a project?
problem 7: What process would you follow to obtain an accurate estimate of a design modification?
problem 8: Describe what earned value analysis is.