The given information is available for three MPS (Master Product Scheduling) items:
Product A: An 80 unit order is to be started in Week 3.
A 55 unit order is to be started in week 6.
Product B: A 125 unit order is to be started in week 5
Product C: A 60 unit order is to be started in week 4.
Build a material requirements plan for items D, E and F. The BOMs (Bill of Materials) are shown in the figure below, and the data from the inventory records are shown in table below. (Warning: The safety stock requirement applies to item F. Be sure to plan a receipt for any week in which the projected on hand inventory becomes less than the safety stock).
Data Category D E F
Lot Sizing Rule FOQ = 150 L4L POQ (P=2)
Lead Time 3 weeks 1 week 2 weeks
Safety Stock 0 0 30
Scheduled Receipts 150 (week3) 120 (week 2) None
Beginning inventory 150 0 100