Ask Management Theories Expert

Supply Chain Planning and Control

Q1. Learning Curve

Benson Racing is training a new pit crew for its racing team. For its first practise run, the pit crew is able to complete all the tasks in exactly 30 seconds. On its second attempt the crew improve by 4.5 seconds.
a) Determine the learning rate based on the above timings.
b) It has been determined that the crew should complete all tasks in 15 seconds to be competitive. How many times will the crew need to practise to reach this target?
c) Is it realistic to expect the crew to improve indefinitely?

Q2. Capacity Decisions

Consider the two capacity options for Arktec Manufacturing shown below:

 

Annual Fixed Costs

Variable Cost per Unit

Option 1

€500,000

€2

Option 2

€100,000

€10

The following are three scenarios identified by Arktec:

Annual Demand

Probability

25,000

30%

60,000

40%

100,000

30%

a) What is the expected value of each option? Which option should be chosen based on these values?

b) If the lowest and highest estimates are updated to 40,000 and 110,000 respectively, what would be the updated expected values? Explain what has happened.

c) Draw the decision tree for Arktec Manufacturing using initial data. You are to assume that a capacity option is chosen before demand levels are known.

d) Calculate the expected value for each branch. Which option would you choose and why?

Q3. Sales & Operational Planning

Flynn Commercial Freezer Ltd. (FCF Ltd), makes commercial and industrial freezers (the kind hotels and restaurants use, and has the aggregate demand requirements for the next six months as given in the table below as are the costs and other necessary data. The firm has regular capacity for 820 units, and overtime capacity for 40 more. Currently, subcontracting can supply up to 100 units per month and this is unlikely to change in the near future.



Month

Demand

 

Costs and other data

1

440

 

Previous output level

460 units

2

480

 

Beginning inventory

0 units

3

520

 

Stockout cost

€800 per unit

4

500

 

Inventory holding cost

€400 per unit at end of month

5

420

 

Unit Cost, regular time

€1,500 per unit

6

400

 

Subcontracting

€2,100 per unit

 

 

 

Unit Cost, overtime

€1,800 per unit

 

 

 

Hiring workers

€200 per unit

 

 

 

Firing workers

€500 per unit

FCF Ltd is considering one of the following three aggregate plans:

Plan A is to produce level quantity, incurring back orders and inventory charges,

Plan B is to produce a base quantity of 800, using first, overtime, then subcontracting, to meet demand and Plan C, a chase plan, using overtime and then subcontracting if regular capacity is insufficient to cover monthly demand.

The company wishes to minimise costs.

Note: there is no need to start and end on the same output level.

FCF Ltd has asked you to recommend one of the plans. Prepare each of the plans, calculate the costs associated with each plan and make a recommendation.

Q4. Scheduling

(a) A particular operation uses a two-step sequence that all jobs in a certain category follow. For the group of jobs listed below;

 

Processing time (minutes)

Jobs

a

b

c

d

e

Workstation A

27

18

70

26

15

Workstation B

45

33

30

24

10

(i) Find the sequence that will minimise the total completion time.

(ii) Construct a progress chart for the sequence of jobs. Clearly identify the amount of idle time at workstation B and the makespan of the batch of jobs.

(iii) What jobs are candidate for splitting? Why? If they were split, how much would idle time and makespan time be reduced? (Assume splitting the jobs in half)

(b) The table below contains information concerning four jobs that are awaiting processing at a work centre.

Job

Processing Time (days)

due date (days)

A

15

28

B

12

20

C

8

30

D

10

26

(i) Sequence the jobs using the SPT, EDD and Critical Ratio priority rules.

(ii) For each of the job sequences from part (i) calculate the mean flow time, the mean number of jobs at the work centre, the mean tardiness, the maximum lateness and the number of late jobs.

(iii) Which sequence performs best for this batch of jobs?

Harvard referencing system.

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M92758581
  • Price:- $90

Guranteed 48 Hours Delivery, In Price:- $90

Have any Question?


Related Questions in Management Theories

Assignment -for this assignment analyze and discuss your

Assignment - For this assignment, analyze and discuss your personal leadership style. Based on your experiences, current readings, work experience, education, and use of self-assessment instruments describe what you thin ...

Assignment -personal reflection 1 -instructions - watch

Assignment - Personal Reflection 1 - Instructions - Watch Milgram's obedience video: Milgram Experiment Proves We Blindly Obey Authority. Consider the following. Christ called his disciples to follow him (Mark 1:17). He ...

Assignment -instructions - please follow instructions for

Assignment - Instructions - Please follow instructions for all for Personal Learning Journal. And each personal learning journal should be of 300words. Each student will keep a personal journal to reflect and record thei ...

Healthcare information technology overview the current

Healthcare Information Technology Overview: The current healthcare industry utilizes a plethora of healthcare information technology (HIT) systems. HIT systems are designed to enhance quality outcomes, prevent adverse ev ...

Archetypes in actionsenge ross smith roberts amp kleiner

Archetypes in Action Senge, Ross, Smith, Roberts, & Kleiner (1994) noted: At its broadest level, systems thinking encompasses a large and fairly amorphous body of methods, tools, and principles, all oriented to looking a ...

Assessment descriptionyou are required to read the

Assessment Description You are required to read the following journal article article: 1. How Risky is Your Company? HBR. May-June 1999 You are also required to read a fictional case study based on a company that will be ...

Discussion - this discussion deals with the important topic

Discussion - This Discussion deals with the important topic of whether money is a motivator for increased job performance and satisfaction. Look at your own history of how you have been compensated, what problems you saw ...

Question - choose a product or technology interview five

Question - Choose a product or technology. Interview five consumers who buy that product and ask them what major problems they have with the product (or what major things they dislike about it). Then ask them to describe ...

Questions -1 choose an industry and then use the library or

Questions - 1. "Choose an industry and then use the library or the Internet to find data from secondary sources that will be highly useful in developing a marketing plan." Start thinking of the industry that relates to t ...

Developing leaders and organisations assessment - report on

Developing, Leaders and Organisations Assessment - Report on Promoting Individual Informal Workplace Learning Brief - You are the newly-appointed Human Resource Advisor in a medium-sized business that employs approximate ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As