Question: The process of designing and implementing a website for commercial use can be described as follows. First, the customer and the web design team have an informational meeting for half a business day. If the first meeting is successful, the customer and the web design team meet again for a full day to work on the storyboard of the site. If the first meeting is not successful, then the process is over, which means the customer will look for another web designer. After the storyboard is completed, the site design begins; immediately after that, the site is developed. The design of the site typically takes 10 business days. The development of the site requires 2 business days. While the site is being designed and developed, the contents are prepared. It takes 5 business days to complete an initial draft of the contents. After the initial draft is completed, a decision is made to have a marketing team review the initial draft.

Experience shows that about 60% of the time the marketing review is needed and 40% of the time the final version of the contents is prepared without the marketing review. The marketing review requires 3 business days, and the preparation of the final version requires 4 business days. The contents are then put into the site. This activity is referred to as building. (Note that before the building can be done, the development of the site and the contents must be completed.) Building the site takes about 3 business days. After the site is built, a review activity is completed to check that all links and graphics are working correctly. The review activity typically is completed in 1 business day. The final activity is the approval of the site, which is done in half a business day. About 20% of the time, the sites are not approved. When a site is rejected, it is sent back to the building activity. When the site is approved, the design process is finished.

a. Draw a flowchart of this process.

b. Calculate the CT.

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M92272542

Have any Question?


Related Questions in Management Theories

Identify three reasons that a project can fail explore each

Identify three reasons that a project can fail, explore each of the reasons, propose a solution that will eliminate the problem and turn the initiative into a success. Use a minimum of two peer reviewed sources. The work ...

This case study relates to the firestone tyre company in

This case study relates to the Firestone Tyre Company in the United States in 2000, and refers to the now famous tyre recall that took place during August of that year. You have been provided with case study details in t ...

In this unit we learned about management organizational

In this unit, we learned about management, organizational structures, and open and closed systems. Write an essay in which you expand on the following topics: Describe management, organization, and leadership in relation ...

Looking at leadership through complexityleading

Looking at Leadership Through Complexity Leading knowledge-based companies is different from leading industrial-based companies (Uhl-Bien & Marion, 2008). The authors noted "complexity leadership theory, a leadership par ...

Questions -1 choose an industry and then use the library or

Questions - 1. "Choose an industry and then use the library or the Internet to find data from secondary sources that will be highly useful in developing a marketing plan." Start thinking of the industry that relates to t ...

Suppose that for a given patient the true ef is 63 consider

Suppose that, for a given patient, the true EF is 63. Consider the population of EF values that can be estimated on that patient using option II above. That population follows a normal distribution with μ= 63. Find the p ...

Assignment overview -this assessment item requires you to

Assignment Overview - This assessment item requires you to consider:- The operation of diverse and complex government and non-government project contractural arrangements relevant to a range of managed services, ICT, and ...

Discussion assignment -the overall design and costs of an

Discussion Assignment - The overall design and costs of an organization's benefits plans are an important part of their people strategy for attracting and retaining a talented workforce. For example, health care costs ar ...

Questionthere is no consensus on a definition of complex

Question: There is no consensus on a definition of complex systems or complex adaptive systems. Both terms are frequently used interchangeably within the literature. Rather, it is much easier to look at the characteristi ...

Questionassume the role of presenter at a conference on

Question: Assume the role of presenter at a conference on organizational development, and then develop a PowerPoint presentation that addresses the following: Explain the importance of top-level leadership in organizatio ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As