Question 1 of 16 4.0 Points

Six (6) samples of size five (5) were used to collect the data presented below:
sample number

1

2

3

4

5

6
sample mean (x-bar)

8.0

8.1

7.9

8.2

7.8

8.0
sample range (R)

1.8

2.4

1.9

1.8

2.1

2.0

The lower control limit (LCL) an x-bar-chart is.
A. LCL = 7.800
B. LCL = 7.034
C. LCL = 6.846
D. LCL = 21.000
E. LCL = 0.000
Reset Selection

Question 2 of 16 4.0 Points

Twenty samples of size six (6) were collected for a variable measurement. Determine the upper control limit (UCL) and lower control limit (LCL) for an R-chart if the average range, Rbar, is 4.4.
A. LCL = 0.3344, UCL = 9.3016
B. LCL = 0.0000, UCL = 1.4696
C. LCL = 1.826, UCL = 6.974
D. LCL = 0.0000, UCL = 8.8176
E. LCL = 0.0000, UCL = 176.3520
Reset Selection

Question 3 of 16 4.0 Points
Twenty-five samples of size thirty (30) were collected and a total of 48 nonconforming items were found yielding p-bar = 0.064. The three sigma upper control limit (UCL) for a p control chart would be
A. 0.833
B. 0.211
C. 0.198
D. 0.091
E. None of the above
Reset Selection

Question 4 of 16 2.0 Points

A company has calculated its CFE to be 700 and its MADt is 20. Which one of the following is the resulting TS?
A. About 0.05
B. About 20
C. About 35
D. More than 35
E. Cannot be calculated based on this information
Reset Selection

Question 5 of 16 2.0 Points
If you were trying to select a forecasting model based on a MAD statistic, which of the following MAD values reflects the most accurate model?
A. 0.425
B. 0.877
C. 2.000
D. 4.599
E. 100
Reset Selection

Question 6 of 16 3.0 Points

Given the following weekly demand and forecast figures:
Week

Demand

Forecast
1

20

40
2

25

20
3

35

30

The MAD is:
A. 0
B. -10
C. 30
D. 10
E. none of the above
Reset Selection

Question 7 of 16 3.0 Points


Given the following weekly demand and forecast figures:

Week

Demand

Forecast
1

20

40
2

25

20
3

35

30

The mean square error is:
A. -10
B. 15
C. 30
D. 150
E. 450
Reset Selection

Question 8 of 16 3.0 Points


A company wants to forecast its demand using the Simple Moving Average and has the following demand data.

Week

Demand
1

120
2

100
3

140
4

120
5

200


Which of the following is the four-period moving average forecast for period 6?


A. 120
B. 136
C. 140
D. 170
E. none of the above
Reset Selection

Question 9 of 16 3.0 Points
A company wants to forecast its demand using the Weighted Moving Average. The company uses two prior yearly sales values (i.e., Year 1 = 110 and Year 2 = 130). Using weights 0.9 and 0.1 with largest weight to demand assigned to the most recent period, which of the following is the two-period Weighted Moving Average forecast for Year 3?
A. 112
B. 117
C. 120
D. 128
E. none of the above.
Reset Selection

Question 10 of 16 3.0 Points
In Period 7 the exponentially smoothed forecast was 50 and the actual demand was 60. If alpha = 0.1, what is the exponentially smoothed forecast for Period 8?
A. 49
B. 50
C. 51
D. 59
E. 61
Reset Selection

Question 11 of 16 3.0 Points

Monthly demand for a product has been as follows in the last 2 months.
July

60 units
August

62 units

What is the forecast for September using exponential smoothing with alpha = 0.2 if the forecast for July was 50 units?
A. 54
B. 53
C. 52
D. 51
E. 50
Reset Selection

Question 12 of 16 4.0 Points

The following table gives the demand and production plan for an organization.

January February March
Demand 900 900 1,500
Production plan 1,100 1,100 1,100

The initial inventory is zero. The inventory holding cost is $1 per unit per month. The total inventory holding cost for the plan is:
A. $400
B. $600
C. $800
D. $1,200
E. None of the above
Reset Selection

Question 13 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The production requirement for the month of February is
A. 300
B. 100
C. 225
D. 250
E. none of the above
Reset Selection

Question 14 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The beginning inventory for the month of March is
A. 60
B. 75
C. 100
D. 150
E. none of the above
Reset Selection

Question 15 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The number of units current work force of 12 workers can produce in a month during regular time is
A. 960
B. 800
C. 640
D. 600
E. none of the above
Reset Selection

Question 16 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The number of workers needed to produce 960 units in a month is
A. 18
B. 16
C. 15
D. 12
E. none of the above
Reset Selection








Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M9585704

Have any Question?


Related Questions in Management Theories

Questionthere are several types of networks while the

Question: There are several types of networks; while the concepts are the same, only the names of the elements change. A network is a set of nodes connected by links, for example. However, some of the academic literature ...

Question 1supply chain management is instrumental as it

Question: 1. Supply chain management is instrumental as it pertains to marketing as marketing plays a key role in integrating supply chain processes and promoting collaboration between stakeholders. 2. In this week's dis ...

Assignment -for this assignment analyze and discuss your

Assignment - For this assignment, analyze and discuss your personal leadership style. Based on your experiences, current readings, work experience, education, and use of self-assessment instruments describe what you thin ...

This case study relates to the firestone tyre company in

This case study relates to the Firestone Tyre Company in the United States in 2000, and refers to the now famous tyre recall that took place during August of that year. You have been provided with case study details in t ...

Fully answer the assigned questions in narrative third

Fully answer the assigned questions in narrative, third person format. The paper consist of 1200 WORDS. Also, include at least three (3) scholarly sources in your responses. Paper must be completed in APA format. NO PLAG ...

Archetypes in actionsenge ross smith roberts amp kleiner

Archetypes in Action Senge, Ross, Smith, Roberts, & Kleiner (1994) noted: At its broadest level, systems thinking encompasses a large and fairly amorphous body of methods, tools, and principles, all oriented to looking a ...

Question - choose a product or technology interview five

Question - Choose a product or technology. Interview five consumers who buy that product and ask them what major problems they have with the product (or what major things they dislike about it). Then ask them to describe ...

Discussion please locate one peer-reviewed journal

Discussion : Please locate one peer-reviewed journal (Scholarly Journal Article) related to the topic: Strategic Communication for Business and the Employee. This assignment must a professionally designed PowerPoint Pres ...

What is the difference between a linear quadratic and cubic

What is the difference between a linear, quadratic, and cubic regression analysis? Please provide a reference.

Benchmark - community teaching plan community

Benchmark - Community Teaching Plan: Community Presentation Note: This is an individual assignment. Based on the feedback offered by the provider, identify the best approach for teaching. Prepare a presentation to accomp ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As