QUESTION 1: A group volunteered to keep a section of highway clean. This is an example of a project.

True

False

QUESTION 2: The sponsor provides the funds to accomplish the project.

True

 False

QUESTION 3: The introduction of a new process to ship packages for a firm is an example of a project objective.

True

 False

QUESTION 4: Resources are identified and selected during the

a. Initiating phase

b. Planning phase

c. Performing phase

d. Closing phase

QUESTION 5: While performing work, all the activities in the baseline plan must be performed in accordance to

a. What the person responsible for the activity wants to do

b. Lessons learned from previous projects

c. How the sponsor has completed all their projects in the past

d. The project schedule and technical specifications.

QUESTION 6: Every project that is identified is selected to be completed.

True

False

QUESTION 7: The project charter is also called a project authorization or a project initiation document.

True

False

QUESTION 8: Projects that are not similar cannot be compared when making a selection to move forward with a project.

True

False

QUESTION 9: An assumption for a construction project could be

a. the materials used to construct the building

 b. a grant will be secured to help fund the project

 c. the regulations and the codes required for the building

 d. the size of the building to be constructed

QUESTION 10: The implementation of the new procedure is expected to reduce costs of production by 10% over the next year. This is an example of the ________________ in a project charter.

a. acceptance criteria

b. project objective

c. project description

d. success criteria and expected benefits

QUESTION 11: It is unethical to submit an unsolicited proposal to a customer.

True

False

QUESTION 12: A contractor should only respond to RFPs if they have the required resources already on their staff.

True

False

QUESTION 13: If the RFP format requirement states a page limit, the customer can reject a proposal that exceeds the page limit without any further review.

True

False

QUESTION 14: Customers and partner organizations prefer to work with people they

a. know are very large with many employees

b. know and trust

c. know are lean companies with few employees

d. have read about

QUESTION 15: You are reading an article about butterfly migration and remember that John from XYZ Company studied lepidopterology. You decide to

a. Send John a copy with a note that you thought it might be of interest to him.

b. Not bother John thinking he must have already read the article.

c. Send John a copy of the article with a note saying how displeased you are with the latest political elections.

d. Print a copy of the article and put it in your file in case john stops in some day.

QUESTION 16: The project scope document defines what needs to be done.

True

False

QUESTION 17: The work breakdown structure can include specifications regarding size, color, weight, or performance parameters such as speed, uptime, throughput, processing time, or operating temperature that the project result must satisfy.

True

False

QUESTION 18: A network diagram is a technique for organizing and subdividing all the project work and deliverables into more manageable components.

True

False

QUESTION 19: Although major or key deliverables may be stated in the project charter or request for proposal, they need to be ___________________ in the project scope document.

repeated

expanded on in greater detail

stated at higher levels

listed in sequence with the responsible person or organization.

QUESTION 20: The ______ is a roadmap that displays how all the specific activities fit together to accomplish the project work scope.

a. work breakdown structure

b. project scope statement

c. project plan

d. network diagram

QUESTION 21: The project manager establishes the parameters and guidelines for what needs to be done, and then tells the project team members how to get it done.

True

False

QUESTION 22: The capable project manager understands what motivates team members and creates a competitive environment in which individuals compete as part of a high-performing team and are required to excel.

True

False

QUESTION 23: The capable project manager provides opportunities for learning and development by encouraging individuals to assume the initiative, take risks, and make decisions.

True

False

QUESTION 24: The project manager has primary responsibility for_______ in planning, organizing, and controlling the work effort to accomplish the project objective.

a. Doing the paperwork

b. Making all of the decisions

c. Providing leadership

d. Impeding

QUESTION 25: The project manager reviews the plan with the customer to gain endorsement and then sets up a project management information system for

a. Recording the plan

b. Solidifying the agreement of the plan

c. Comparing actual progress to planned progress

d. Using technology to appear competent

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M91914219
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Management Theories

Chapter- gravity modela manufacturer of cat towers wishes

Chapter- Gravity Model A manufacturer of cat towers wishes to locate a super assembly facility to meet their cat tower assembly needs for the next millennium. Currently, carpet, cylinders, yarn and fasteners are purchase ...

Assignmentlearning outcome recognize the impact of

Assignment Learning Outcome: Recognize the impact of organizational culture on shaping values, attitudes and behavior. Case Study: Foundations of Individual Behavior Differing Perceptions at Clarkston Industries Susan Ha ...

Identify a health technology or a specific aspect of a

Identify a health technology or a specific aspect of a payment system that is changing for your health care setting. Work as a team to prepare a PowerPoint presentation to educate and inform your co-workers about the rec ...

Questions -1 choose an industry and then use the library or

Questions - 1. "Choose an industry and then use the library or the Internet to find data from secondary sources that will be highly useful in developing a marketing plan." Start thinking of the industry that relates to t ...

Question - choose a product or technology interview five

Question - Choose a product or technology. Interview five consumers who buy that product and ask them what major problems they have with the product (or what major things they dislike about it). Then ask them to describe ...

What is the difference between a linear quadratic and cubic

What is the difference between a linear, quadratic, and cubic regression analysis? Please provide a reference.

Business research assignments -assessment 1 - literature

Business Research Assignments - Assessment 1 - Literature Review (2000 to 2500 words) For this assessment, students are expected to demonstrate their understanding of the extant, academic literature related to an approve ...

Discussion - this discussion deals with the important topic

Discussion - This Discussion deals with the important topic of whether money is a motivator for increased job performance and satisfaction. Look at your own history of how you have been compensated, what problems you saw ...

Assignment overview -this assessment item requires you to

Assignment Overview - This assessment item requires you to consider:- The operation of diverse and complex government and non-government project contractural arrangements relevant to a range of managed services, ICT, and ...

Case study assignment -case description liang global

Case Study Assignment - Case Description: Liang Global Solutions (LGS) operates in the six New England states. LGS faced an important decision: selecting network software that would maximize functionality, manageability, ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As