QUESTION 1

Allen is managing a new product development project.

The Plan:

·The project consists of five different activities. Each activity is expected to take twenty hrs. Further, · every activity has four sub-activities that each take 5 hours. · Allen hires five resources. They will each work on 20% of the project parallelly and will be paid $100/ hr. The total estimated project is $10,000. · Based on the distribution of work, it is determined that the project can be completed within a week.

Progress Measurement:

Initial Reports · At the end of the week, the resources are asked to submit their recorded timesheets. · Total hours reported by all team members is 90hrs.· Based on this information, Allen quickly assumes the project is 90% complete. · Allen then decides that the project will be delayed. Allen sends a status report claiming that the project is within budget but not on time.

a) Would you agree with Allen's assessment of the project? Justify your answer in detail with reasons.

Allen now calls each programmer and gathers the following information:

Programmer

Budgeted Time

Actual time spent

Invoices Submitted

Percentage of all tasks completed

Bob

20 hours

15 hours $1.500 60%

Sue

20 hours

25 hours $2.500 75%

Roger

20 hours

5 hours $500 10%

Mike

20 hours

30 hours $3,000 50%

Jill

20 hours

15 hours $1500 80%

Total time and
costs incurred

 

90 hours 99,000

 

Table 1

Using the data given:

b) Calculate SV, SPI
c) Calculate CV, CPI
d) Discuss the meaning of each of these indicators and so, the health of the project.

QUESTION 2

Delicious Foods LLC, a 15-year-old fast food company has a production factory in Geneva. They require meat and produce including fruits and vegetables as raw materials. Procurement is done through local suppliers at each location. Transportation is done by a third-party service provider, who does not value the preservation of perishables. Almost, 35% of the materials are lost due to improper storage, temperature control, etc. There is also a growing concern regarding their delayed deliveries.

Though the customers love the product, the company struggles with timely delivery and improper packing, which does not preserve products for long, with shelf life of only about 6 hrs., if not kept under temperature-controlled conditions. Though the company has over 15 distributors there is no coordination or centralization. The information systems are primitive and are steadily losing customers to growing competitors. You are appointed as a logistics consultant. You are required to put forward your suggestions with regards to improving the following:

a) Purchasing and distribution system
b) Alternative transportation
c) Any other areas

Assignment 1:

Cost and Schedule Control

You are managing a small project which includes building a boundary wall for a square plot. The wall is exactly the same on each of the four sides. Assumption: time and costs for each side will be same. Estimated duration of the project is 8 days to complete and the budget, including contingency reserves for risks is $12,000.

At the end of 4 days, you need to report the progress of the project. Are asked to prepare ayou decide to use the Earned Value calculation in order to determine the health of the project. The team reports that end of day 4, total costs incurred are $5,500. And 30% of the project is completed.

Calculate
SV, CV, SPI, CPI. What do these indicate about the status of the project? Interpret your results in terms of schedule and cost progress.
Suggest one best action corrective (if applicable) and justify your recommendations.

Assignment 2:

QUALITY ASSURANCE AND AUDIT

Refer to the Self Assessment form on Quality Assurance and Audit, Chapter 1 Slide no. 11, Category4 Measurement, Analysis and Knowledge Management.

For each of the points from 4a to 4f, if you have marked Strongly Agree / Agree discuss the existing process within your organization to explain how it is done.

E.g. for 4a Discuss how exactly is the quality of your work measured. Write down the Key Performance Indicators used.

If you have marked Neither Agree nor disagree / Disagree / Strongly Disagree, suggest how the same could be achieved.

e.g. for 4a Discuss how exactly you think the quality of your work can be measured. Write down the Key Performance Indicators which you can use.

This needs to be done for all points from 4a to 4f.

Attachment:- Activity.rar

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M93055729
  • Price:- $25

Priced at Now at $25, Verified Solution

Have any Question?


Related Questions in Management Theories

Assignment -for this assignment analyze and discuss your

Assignment - For this assignment, analyze and discuss your personal leadership style. Based on your experiences, current readings, work experience, education, and use of self-assessment instruments describe what you thin ...

Assignment -personal reflection 1 -instructions - watch

Assignment - Personal Reflection 1 - Instructions - Watch Milgram's obedience video: Milgram Experiment Proves We Blindly Obey Authority. Consider the following. Christ called his disciples to follow him (Mark 1:17). He ...

Assignment -instructions - please follow instructions for

Assignment - Instructions - Please follow instructions for all for Personal Learning Journal. And each personal learning journal should be of 300words. Each student will keep a personal journal to reflect and record thei ...

Healthcare information technology overview the current

Healthcare Information Technology Overview: The current healthcare industry utilizes a plethora of healthcare information technology (HIT) systems. HIT systems are designed to enhance quality outcomes, prevent adverse ev ...

Archetypes in actionsenge ross smith roberts amp kleiner

Archetypes in Action Senge, Ross, Smith, Roberts, & Kleiner (1994) noted: At its broadest level, systems thinking encompasses a large and fairly amorphous body of methods, tools, and principles, all oriented to looking a ...

Assessment descriptionyou are required to read the

Assessment Description You are required to read the following journal article article: 1. How Risky is Your Company? HBR. May-June 1999 You are also required to read a fictional case study based on a company that will be ...

Discussion - this discussion deals with the important topic

Discussion - This Discussion deals with the important topic of whether money is a motivator for increased job performance and satisfaction. Look at your own history of how you have been compensated, what problems you saw ...

Question - choose a product or technology interview five

Question - Choose a product or technology. Interview five consumers who buy that product and ask them what major problems they have with the product (or what major things they dislike about it). Then ask them to describe ...

Questions -1 choose an industry and then use the library or

Questions - 1. "Choose an industry and then use the library or the Internet to find data from secondary sources that will be highly useful in developing a marketing plan." Start thinking of the industry that relates to t ...

Developing leaders and organisations assessment - report on

Developing, Leaders and Organisations Assessment - Report on Promoting Individual Informal Workplace Learning Brief - You are the newly-appointed Human Resource Advisor in a medium-sized business that employs approximate ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As