A consumer electronics firm is planning an expansion into Milwaukee. Generally, the firm prefers to remodel large existing tenant spaces to suit their needs. After a site is selected from several alternatives, the corporate architect develops plans by reviewing the suitability of existing structure and utilities. A modification and demolition plan is then developed. Interior finish plans are then developed from corporate standards and adjusted to each site.
Building permits are handled by the general contractor (GC). The firm uses the GC for all of its construction in a region. The GC hires local subcontractors and provides on-site construction supervision.
As construction begins, the firm also begins to assemble a new management team from existing management staff, making an attempt to use only staffs that has an interest in relocating. Sales staff is hired locally.
When construction is approximately six weeks from completion, inventory is ordered.
Prepare a work breakdown structure (WBS) for this project with activities corresponding to a two level task and sub-task hierarchy. Provide columns showing the WBS code and activities. Number and indent the WBS codes so that the level of each activity is clearly identified.
Additional Requirements