Now that you have a solid understanding of how Earned Value Management is conducted and how to use the EVM Tool, understand that many organizations do not use such tools but rely on the basic principles you have learned in this course. As such, you now have the opportunity to display your understanding of EVM principles using just the basic formulae. You may use any tools we have utilized in this course (Excel, MPP, EVM tool) or you may calculate the assignment longhand.

Project Background:

Note: The following problem is taken from a standardized, globally-used EVM assessment and reflects the basics of EVM. To maintain their competitive position in the robotics market, the RAMBOTICS Corporation needs to develop a new generation robot. They have initiated a project to achieve this goal. The project will commence in six months. The project is comprised of the tasks in Table 1: Original Task List and Budgeted Effort. Predecessors, task duration, and the number of personnel required to achieve the task in that duration are also provided.

Part 1: Requirements

Construct a Gantt Bar Chart for the project and determine Budget At Completion (BAC) for the project. Assume that RAMBOTICS Corporation has access to unlimited resources; that personnel cost are blended costs at $10,000 per month per person, and that there are no project costs other than personnel costs. A task cannot commence until all its predecessors have been completed.

Table 1: Original Task List and Budgeted Effort

ID

Job Description

Immediate Predecessors

Planned duration (Months)

Staff (Number)

A

Electrical Design

Start

4

6

B

Assemble Boards

A

4

3

C

Test Boards

B

2

2

D

Software Design

Start

4

1

E

Programming

D

2

2

F

Software Testing

E

2

2

G

Robot Body Deign

A

4

2

H

Robot Construction

G

2

2

I

Final Assembly

C, F, H

2

2

Part 2: Earned Value Calculations

After eight months, project progress is determined as detailed in Table 2. Predecessors remain the same.

Table 2: Progress at the End of Month Eight

ID

Job Description

Efforts (Person Months)

Outstanding Duration (Months)

Staff Number

A

Electrical Design

30

0

0

B

Assemble Boards

9

1

3

C

Test Boards

0

2

2

D

Software Design

4

0

0

E

Programming

8

1

2

F

Software Testing

0

4

2

G

Robot Body Design

6

1

2

H

Robot Construction

0

2

2

I

Final Assembly

0

2

2

Part 2: Earned Value Calculations

Using the information in Table 2: Progress at the End of Month Eight and the original details, update your Gantt Chart showing the remaining work, and estimate the PV (BCWS), AC (ACWP), and EV (BCWP) for each task at the end of month eight.

For the project:

  • What is the Cost Variance (CV)?
  • What is the Schedule Variance (SV)?
  • What is the Cost Performance Index (CPI)?
  • What is the Schedule Performance Index (SPI)?
  • What is the Estimate at Completion (EAC)?

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M91412474
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Management Theories

Assignment -for this assignment analyze and discuss your

Assignment - For this assignment, analyze and discuss your personal leadership style. Based on your experiences, current readings, work experience, education, and use of self-assessment instruments describe what you thin ...

Assignment -personal reflection 1 -instructions - watch

Assignment - Personal Reflection 1 - Instructions - Watch Milgram's obedience video: Milgram Experiment Proves We Blindly Obey Authority. Consider the following. Christ called his disciples to follow him (Mark 1:17). He ...

Assignment -instructions - please follow instructions for

Assignment - Instructions - Please follow instructions for all for Personal Learning Journal. And each personal learning journal should be of 300words. Each student will keep a personal journal to reflect and record thei ...

Healthcare information technology overview the current

Healthcare Information Technology Overview: The current healthcare industry utilizes a plethora of healthcare information technology (HIT) systems. HIT systems are designed to enhance quality outcomes, prevent adverse ev ...

Archetypes in actionsenge ross smith roberts amp kleiner

Archetypes in Action Senge, Ross, Smith, Roberts, & Kleiner (1994) noted: At its broadest level, systems thinking encompasses a large and fairly amorphous body of methods, tools, and principles, all oriented to looking a ...

Assessment descriptionyou are required to read the

Assessment Description You are required to read the following journal article article: 1. How Risky is Your Company? HBR. May-June 1999 You are also required to read a fictional case study based on a company that will be ...

Discussion - this discussion deals with the important topic

Discussion - This Discussion deals with the important topic of whether money is a motivator for increased job performance and satisfaction. Look at your own history of how you have been compensated, what problems you saw ...

Question - choose a product or technology interview five

Question - Choose a product or technology. Interview five consumers who buy that product and ask them what major problems they have with the product (or what major things they dislike about it). Then ask them to describe ...

Questions -1 choose an industry and then use the library or

Questions - 1. "Choose an industry and then use the library or the Internet to find data from secondary sources that will be highly useful in developing a marketing plan." Start thinking of the industry that relates to t ...

Developing leaders and organisations assessment - report on

Developing, Leaders and Organisations Assessment - Report on Promoting Individual Informal Workplace Learning Brief - You are the newly-appointed Human Resource Advisor in a medium-sized business that employs approximate ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As