In this project, you will analyse the situation and the effect of the change request on the schedule, cost, and features. The final project will be based on your answers for Week 4 (Project Proposal) and Week 6 (Project Outline). Your project deliverables will include:

*  A formal change request

*  An evaluation of the impact of the change (as submitted to the Change Control Board)-time and labour only

Note: It will be necessary to create the original project schedule and budget to analyse the impact of the change request. Consider that the additional wing will be built concurrently.

*  A list of all the assumptions made

*  An analysis of the risk factors due to the change request

*  A new project schedule that shows:

o  The additional time required for constructing the extra wing

o  The additional labour cost for constructing the extra wing

o  The new completion date

*  A statement of work for one contractor

*  A contract closure process description for one contractor

*  A project closure process description

The project details are as follows:

The Smiths purchase a piece of land and decide to build a house on it. They consult an architect and have blueprints created. You are a general contractor and agree to build the house for them.

You estimate it will take 12 weeks to complete the house. However, you need contingency time to accommodate the uncertain weather conditions, so you tell the Smiths you need 14 weeks. The Smiths are really anxious to move into their new house. So, although they agree for 14 weeks, they want to put in a late-completion penalty in the agreement. You agree, provided they also put in a bonus for early completion. You all sign the contract.

You estimate the project duration and effort as follows:

Task

Duration (days)

Effort (staff days)

Comments

Get a building permit.

5

1

 

Clear the site.

5

20

 

Dig the foundation and footings.

3

9

 

Install forms.

3

9

 

Pour concrete.

1

5

 

Wait for the concrete to harden.

5

0

This is referred to as lag time.

Remove forms.

1

3

 

Build the floor.

1

5

 

Frame the first floor.

2

10

 

Build the second floor.

2

10

 

Frame the second floor.

3

15

 

Sheath the house.

3

12

 

Install windows and doors.

4

8

 

Install siding.

2

6

 

Put up roof framing.

2

8

Can start as soon as the second floor is framed

Shingle the roof.

1

4

 

Install plumbing.

4

8

Can start as soon as the roof is shingled

Inspect the plumbing.

1

0

 

Install wiring.

6

12

Can start as soon as the roof is shingled

Inspect the wiring.

1

0

 

Hang and finish sheetrock.

4

12

Can start only after the plumbing and electrical work are inspected

Paint the interior.

3

9

 

Lay the carpet.

2

6

 

Install the hardwood flooring.

3

6

 

Install trim.

3

6

 

Procure the certificate of occupancy.

5

0

 

Total

75

184

 

Just as your crew starts framing the second floor, the Smiths tell you that they want an additional wing in the house. They give you a new set of blueprints containing the new wing and ask for a projected difference in price and time for the addition.

You determine that to add an extra wing, you would require the following in terms of duration and effort:

Task

Duration (days)

Effort (staff days)

Comments

Dig the foundation and footings.

2

6

 

Install forms.

2

6

 

Pour concrete.

1

3

 

Wait for the concrete to harden.

5

0

This is referred to as lag time.

Remove forms.

1

2

 

Build the floor.

1

4

 

Frame the first floor.

1

4

 

Build the second floor.

1

4

 

Frame the second floor.

2

8

 

Sheath the house.

2

6

 

Install windows and doors.

2

4

 

Install siding.

1

3

 

Put up roof framing.

2

6

 

Shingle the roof.

1

3

 

Install plumbing.

2

4

 

Inspect the plumbing.

     

Install wiring.

2

4

 

Inspect the wiring.

     

Hang and finish sheetrock.

2

6

 

Paint the interior.

1

3

 

Lay the carpet.

2

4

 

Install the hardwood flooring.

     

Install trim.

1

3

 
       

Total

34

83

 

This new estimate assumes the sheathing will go on the base house and then work will stop until the extra wing is sheathed. You believe this to be the most economical way to add the additional wing. Another option is to continue the project as originally planned and then to add the wing after the Smiths move in. After considering both options, the Smiths decide to follow your recommendation-to add the new wing before they move in. The additional work required is as follows:

Task

Duration (days)

Effort (staff days)

Comments

Procure the building permit.

5

1

 

Dig the foundation and footings.

2

6

 

Install forms.

2

6

 

Pour concrete.

1

3

 

Wait for the concrete to harden.

5

0

 

Remove forms.

1

2

 

Build the floor.

1.5

6

 

Frame the first floor.

1.5

6

 

Build the second floor.

1.5

6

 

Frame the second floor.

2

8

 

Add the sheath.

2

6

 

Install windows and doors.

2

4

 

Install the siding.

1

3

 

Put up roof framing.

2.5

7

 

Shingle the roof.

1

3

 

Install plumbing.

2

4

 

Inspect the plumbing.

1

0

 

Install wiring.

2

4

 

Inspect the wiring.

1

0

 

Hang and finish sheetrock.

2

6

 

Paint the interior.

1

3

 

Lay the carpet.

2

4

 

Install trim.

1

3

 
       

Total

38

90

 

The rates for the various trades (in $/hour) are as follows:

Code

Description

Rate

Comments

GC

General contractor

40.00

 

HE

Heavy-equipment operator

50.00

Includes equipment

C

Concrete worker

30.00

 

F

Framer

20.00

 

F

Siding installer

20.00

 

W

Window/door installer

30.00

 

R

Roofer

20.00

 

P

Painter

20.00

 

E

Electrician

35.00

 

FL

Flooring installer

20.00

 

T

Trim carpenter

35.00

 

PL

Plumber

35.00

 

 2500 words

Original work tested through turnitin

Graphs and tables using Microsoft project or open-project

3 references and more

Use citing and citation with Harvard system

If you need the project proposal and project outline from week 6 & 8 work let me know

 

 

 

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M9880140
  • Price:- $100

Priced at Now at $100, Verified Solution

Have any Question?


Related Questions in Management Theories

Questions -1 choose an industry and then use the library or

Questions - 1. "Choose an industry and then use the library or the Internet to find data from secondary sources that will be highly useful in developing a marketing plan." Start thinking of the industry that relates to t ...

Case study assignment -case description liang global

Case Study Assignment - Case Description: Liang Global Solutions (LGS) operates in the six New England states. LGS faced an important decision: selecting network software that would maximize functionality, manageability, ...

This case study relates to the firestone tyre company in

This case study relates to the Firestone Tyre Company in the United States in 2000, and refers to the now famous tyre recall that took place during August of that year. You have been provided with case study details in t ...

Assignment -for this assignment analyze and discuss your

Assignment - For this assignment, analyze and discuss your personal leadership style. Based on your experiences, current readings, work experience, education, and use of self-assessment instruments describe what you thin ...

The following are amounts of time minutes spent on hygiene

The following are amounts of time (minutes) spent on hygiene and grooming in the morning by survey respondents (based on data from an SCA survey). 15, 16, 18, 25, 26, 30, 32, 41, 45, 55, 63. Does the number 63 appear unu ...

Styles of leadershipinstructionsama style with

Styles of Leadership Instructions AMA style with references When preparing for your discussion post on this case, it is recommended that you read through it several times. Read through it the first time to familiarize yo ...

Questionthe class examined the joint commissions framework

Question: The class examined the Joint Commission's framework for root cause analysis of sentinel incidents in health care organizations. For purposes of this project, a critical incident is a key occurrence, but it is n ...

Assessment descriptionyou are required to read the

Assessment Description You are required to read the following journal article article: 1. How Risky is Your Company? HBR. May-June 1999 You are also required to read a fictional case study based on a company that will be ...

Team projectprepare an evaluation of quality within the

Team Project Prepare an evaluation of quality within the organization chosen by the team Use information learned in this course and in prior courses in statistics or quantitative methods, apply the appropriate tools to f ...

A surgical technique is performed on nine patients you are

A surgical technique is performed on nine patients. You are told there is 70% chance of success. Find the probability that the surgery is successful for exactly 6 patients.

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As