Review this case carefully and answer the questions at the end of the case in detail.

Hub Aerospace, Inc. was awarded a fixed-price-incentive contract for jet aircraft engines. The engines were assembled by Hub from components furnished by subcontractors. Hub had received competitive bids on all their components, which they had compiled, to come up with the bid price. Included in a number of these components was one termed a "chamber?" Hub's make-or-buy study in the pre-contract phase had concluded with the decision to buy 70 chambers from one of its subcontractors.

Mr. Brosky, the contracting officer, had reduced the target price by $58,751 pursuant to the clause on price reductions for defective cost or pricing data. His decision to take this action was based on information furnished him by the GAO, who found in their post-award audit under PL 87-653 that Hub had failed to disclose price quotations submitted by a subcontractor, Steele Tube and Pipe Company, in competition for the chambers. This subcontractor's quotation of 1 February 19X0 to Hub had been a unit price of $16,211. Hub's proposal to the government was based on the unit price of $17,000 submitted by the Weller Steel Tube Company. The difference between these two vendor prices of $789, adjusted by contract pricing arrangement of 75/25, G&A and profit was the basis of Mr. Brosky's price adjustment.

Also at issue is a substantial increase in the amount of price reduction based on another undisclosed quotation of $15,451, 3 June 19X0. This quotation was submitted by Steele after the prime contract negotiations were completed and after Hub had executed its certificate of current pricing but before signing the prime contract. Hub then awarded the subcontract to Steele at the reduced price.

The circumstances preceding award of the government's contract to Hub Aerospace, Inc. were substantially as follows:

The number of chambers to be purchased or to be made in-house under the make-or-buy program was uncertain. Changes were made in the program and in the quantities to be quoted on by the subcontractors. In January 19X0, the range of prices per unit for chambers was as follows:

Quantity

Steele

Weller

76

$18,463.51

$19,283.00

102

18,278.90

18,835.00

128

18,186,59

18,486.00

154

18,094.29

18,228.00

180

17,909.68

17,990.00

On 6 February 19X0, Weller's oral quotation for 144 units was given: $16,866 for deliv beginning in November. On 7 February 19X0. Steele's written quotation for delivery in J 19X0 was submitted as follows:

Quantity

Price Each Lot Of

144

$16,142.58

120

16,179.85

96

16,211.12

The above prices are based on uninterrupted production at rates shown above commencing July 19X0."

The delivery conditions imposed by Steele made their quotations nonresponsive, s Hub's RFQ called for delivery in November, not July. Hub's subcontracting Negotia Memorandum showed an attempt to have Steele eliminate that condition, and their stater they would give some consideration to the effect on pricing if they complied with the deli schedule. The Memorandum contained no evidence to show that when Hub submitted proposal to the Government in March 19X0, or before conclusions of the negotiations in that Steele had eliminated its delivery condition. On the basis of delivery, Hub accepted Well quotation of $16,866 adjusted to $17,000 because of program changes from 144 to 136.

The government's Negotiation Memorandum reflected a close and cooperative relatior between Hub and the government personnel. The cost analyst could have learned of quotation differences by asking for access to the chambers' procurement records, government representatives were familiar with both Steele and Weller and when a make-on decision arose they would be logical subcontracting sources. In relying on the cost and pr data, the government was satisfied with the Weller $17,000 price. However, it had been pr practice when loser prices were known to attempt to secure a lower overall price. This happened with other contractors.

The Negotiation Memorandum also showed concessions by both parties. Each had all its position several times on target cost, profit, share-ratio, and ceiling price. As negotiated, Hub's target cost had been reduced from $12,859 to $9,735, and there had adjustments of profit percentages from the original position of each party. As they finally incorporated in the contract, target costs had been arrived at on a total cost approach.

When Mr. Peterson, Hub's President, met with the contracting officer to discuss the reduction, he was aware of Clause 51 of his contract, providing for a price reduction vy contract has: ". . . furnished incomplete or inaccurate cost or pricing data or data not certified in the contractor's Certificate of Current Cost or Pricing Data. On the other ha was convinced that his firm had not violated either the letter, or the spirit of PL 87-653. Ai exchange of greetings, Mr. Peterson introduced Mr. Blackstone, his attorney, to Mr. Brosky counselor was quick to "get down to the case at hand" presenting to the contracting office company's position that:

Hub does not object to the minor adjustments or the method of adjusting the contract amount, i.e., reducing the contract price by the target cost and target profit attributable to a nondisclosure. Hub objects to any adjustment being made and on the theory, that in the total cost negotiations in this case, the target cost would have been reduced by the entire amount of the difference between the Steele and Weller quotations.

Flub contends that no price adjustment is due because of its failure to disclose Steele's $15,451 price, quoted in June 19X0. Because that quotation was neither solicited nor received until after the 7 May I 9X0 date of certificate of current pricing and until after the prime contract price had been negotiated.

Hub further objects on various grounds to the government's entitlement to adjustments, as included in Mr. Brosky's decision, contending:

(1) Steele's quotation of 1 February 19X0 was not cost or pricing data as of 7 May 19X0 because it was conditioned on an unacceptable delivery schedule, had a 30-day acceptance limitation, and was at that time neither responsive nor current.

(2) The quotation was in fact disclosed to the government prior to or in connection with the contract price negotiations.

(3) If there was a nondisclosure, the government has failed to prove that it caused an overstatement in the contract price. That is the government did not rely on Weller's $17,000 quotation or on the alleged absence of the Steele quotation. In addition to other evidence, the government's conduct in asserting no such claim when chargeable with, knowledge of the facts shows its lack of reliance, its construction of the contract and, perhaps, a waiver of the right to a price adjustment.

QUESTIONS:

1. Evaluate each of Hub's contentions. Do you agree or disagree? Why?

2. What should Mr. Brosky do now?

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M92215299
  • Price:- $12

Priced at Now at $12, Verified Solution

Have any Question?


Related Questions in Management Theories

Assignment -for this assignment analyze and discuss your

Assignment - For this assignment, analyze and discuss your personal leadership style. Based on your experiences, current readings, work experience, education, and use of self-assessment instruments describe what you thin ...

Assignment -personal reflection 1 -instructions - watch

Assignment - Personal Reflection 1 - Instructions - Watch Milgram's obedience video: Milgram Experiment Proves We Blindly Obey Authority. Consider the following. Christ called his disciples to follow him (Mark 1:17). He ...

Assignment -instructions - please follow instructions for

Assignment - Instructions - Please follow instructions for all for Personal Learning Journal. And each personal learning journal should be of 300words. Each student will keep a personal journal to reflect and record thei ...

Healthcare information technology overview the current

Healthcare Information Technology Overview: The current healthcare industry utilizes a plethora of healthcare information technology (HIT) systems. HIT systems are designed to enhance quality outcomes, prevent adverse ev ...

Archetypes in actionsenge ross smith roberts amp kleiner

Archetypes in Action Senge, Ross, Smith, Roberts, & Kleiner (1994) noted: At its broadest level, systems thinking encompasses a large and fairly amorphous body of methods, tools, and principles, all oriented to looking a ...

Assessment descriptionyou are required to read the

Assessment Description You are required to read the following journal article article: 1. How Risky is Your Company? HBR. May-June 1999 You are also required to read a fictional case study based on a company that will be ...

Discussion - this discussion deals with the important topic

Discussion - This Discussion deals with the important topic of whether money is a motivator for increased job performance and satisfaction. Look at your own history of how you have been compensated, what problems you saw ...

Question - choose a product or technology interview five

Question - Choose a product or technology. Interview five consumers who buy that product and ask them what major problems they have with the product (or what major things they dislike about it). Then ask them to describe ...

Questions -1 choose an industry and then use the library or

Questions - 1. "Choose an industry and then use the library or the Internet to find data from secondary sources that will be highly useful in developing a marketing plan." Start thinking of the industry that relates to t ...

Developing leaders and organisations assessment - report on

Developing, Leaders and Organisations Assessment - Report on Promoting Individual Informal Workplace Learning Brief - You are the newly-appointed Human Resource Advisor in a medium-sized business that employs approximate ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As