DELAY CLAIMS

Review this case care/ ully and answer the questions at the end of the case in detail. You are the contracting officer in charge of administration of a contract for the manufacture of aircraft jet engines. The contract was entered into on August 18, l 9XO, for a firm-fixed-price and contains the normal general provisions. The delivery schedule on this contract must be adhered to since the engines are to be furnished to aircraft manufacturers as government -furnished property.

During the performance of this contract the following delays occur:

1. September 10 to October 18, 19XO - on September 10, the contractor informed you that the specifications for the jet engine contained a number of requirements which could not be met if the delivery schedule was to be met. Your review of the specific requirements pointed out by the contractor indicates that they are primarily items that were added to the specification after the last procurement by your technical division.

Your technical people review the items and agree that most of them can be changed back to the previous requirements in order to facilitate meeting the schedule. Your change order accomplishing this reaches the contractor on October 18. In the interim, the contractor has been working on the manufacturing engineering aspect of the contract but has been unable to order long lead time components. He claims 30 days delay.

2. October 12-26, 19XO - a strike of the machinists in the contractor 's plant closes the plant completely.

3. November 3 to December 21, 19XO - on November 3, your technical division informs you that a major change to the rotor section of the engine must be processed since defects have been reported in the field. You order the contractor to conduct an immediate expedited study of this problem under his continuing engineering contract (a separate contract) and to submit a proposed design change in three weeks. Because of the urgency of this redesign your technical people spend the three weeks at the contractor's plant and are able to process the change in 10 days after it is submitted by the contractor. You issue the change on December 7, and the contractor takes two additional weeks to process the change through manufacturing engineering into his plant. He stopped work on the rotor assemblies on November 3, when he found out about the change and therefore claims a delay of the entire 48 days.

4. January 5 to February 7, l 9Xl - on January 5, the Excello Company informed the contractor that they were unable to deliver the subcontracted fuel pump for the engine because they cannot hold the precise tolerances required to manufacture the pump. In previous contracts the contractor had bought these pumps from the Ace Pump Company with no difficulty. However, on this procurement , following the clause in the contract requiring competition in subcontracting to the maximum practical degree, the contractor had awarded the job to Excello on the basis of their low competitive bid. The contractor immediately awarded another contract to Ace with orders to expedite delivery to the maximum. He claims a delay of 33 days.

Facing a delivery schedule calling for initial deliveries on April 15, 19Xl , and knowing that the government would not allow schedule slippage, the contractor began working overtime on December 1, 19XO. As further slippages occurred, he added extra shifts and took all possible steps to expedite progress on the contract. However, it was apparent that he was in trouble and on January 25, 19X1, the head of your agency called a meeting with the contractor to determine what could be done. At this meeting the head of your agency told the contractor that the contract must be performed on schedule and suggested that he take further steps to assure timely delivery.

The contractor worked Saturdays and Sundays from that time on and was able to deliver the initial group of engines at the end of April 19Xl (two weeks late). He now claims compensation for the overtime, shift premmm, loss of efficiency m expediting, subcontractor expediting costs, etc.

QUESTIONS:

How would you handle such a claim? Discuss each of the claimed delays and claim for additional compensation.

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M92498000
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Management Theories

Assignment -for this assignment analyze and discuss your

Assignment - For this assignment, analyze and discuss your personal leadership style. Based on your experiences, current readings, work experience, education, and use of self-assessment instruments describe what you thin ...

Assignment -personal reflection 1 -instructions - watch

Assignment - Personal Reflection 1 - Instructions - Watch Milgram's obedience video: Milgram Experiment Proves We Blindly Obey Authority. Consider the following. Christ called his disciples to follow him (Mark 1:17). He ...

Assignment -instructions - please follow instructions for

Assignment - Instructions - Please follow instructions for all for Personal Learning Journal. And each personal learning journal should be of 300words. Each student will keep a personal journal to reflect and record thei ...

Healthcare information technology overview the current

Healthcare Information Technology Overview: The current healthcare industry utilizes a plethora of healthcare information technology (HIT) systems. HIT systems are designed to enhance quality outcomes, prevent adverse ev ...

Archetypes in actionsenge ross smith roberts amp kleiner

Archetypes in Action Senge, Ross, Smith, Roberts, & Kleiner (1994) noted: At its broadest level, systems thinking encompasses a large and fairly amorphous body of methods, tools, and principles, all oriented to looking a ...

Assessment descriptionyou are required to read the

Assessment Description You are required to read the following journal article article: 1. How Risky is Your Company? HBR. May-June 1999 You are also required to read a fictional case study based on a company that will be ...

Discussion - this discussion deals with the important topic

Discussion - This Discussion deals with the important topic of whether money is a motivator for increased job performance and satisfaction. Look at your own history of how you have been compensated, what problems you saw ...

Question - choose a product or technology interview five

Question - Choose a product or technology. Interview five consumers who buy that product and ask them what major problems they have with the product (or what major things they dislike about it). Then ask them to describe ...

Questions -1 choose an industry and then use the library or

Questions - 1. "Choose an industry and then use the library or the Internet to find data from secondary sources that will be highly useful in developing a marketing plan." Start thinking of the industry that relates to t ...

Developing leaders and organisations assessment - report on

Developing, Leaders and Organisations Assessment - Report on Promoting Individual Informal Workplace Learning Brief - You are the newly-appointed Human Resource Advisor in a medium-sized business that employs approximate ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As