Case Study: Contract & Procurement

Read the Case-Study and answer the questions which follow:

Synopsis :

Having started operations in 1922, the British Broadcasting Corporation (BBC) is one of the world's oldest and most respected media production and broadcasting organizations. Covering both entertainment and news, the BBC's radio and television productions captured the 20th century as it unfolded. The BBC's archive of broadcast materials is unparalleled and as production continues to this day, the corporation has one of the largest archives of media materials in the world. Delivering content through television, radio, the Internet and via the BBC iPlayer app, the BBC is a brand name that is known around the world.

To improve efficiency when creating new materials, and to allow for better management and integration of archive materials, the BBC initiated the "Digital Media Initiative" (DMI) in 2008. DMI was intended to provide a single tool that would enable video and radio production from raw materials through to final edit. Accessible from staff desktops the system was to standardize the tool used for new production while allowing for improved integration of the vast archive of media materials built up over the organization's 90 plus years.

Without going through a formal tender process, the contract to develop DMI was awarded to the BBC's existing technology provider (Siemens) in 2008. The fixed price contract established a plan that would see the project completed in 18 months at a cost £82M. In theory a fixed priced contract protects the buyer from cost overruns, in practice this is not always the case as lack of clarity in requirements, changing needs and other real world complications often leave the door open to continual changes that can impact delivery dates and costs. Such was the case for DMI and ongoing challenges creating the system resulted in a Jul 2009 "no-fault" termination of the contract. Bringing the project back in house the BBC revised the timeline and set about completing the project using their own internal technical team. An independent audit report by the National Audit Office at the time made note of the failure to conduct a competitive tender process and made a number of recommendations to help ensure the system could be delivered by the internal team.

As work proceeded still further problems were encountered. Internally there was growing concern at the lower levels of project that senior levels were not being given a true picture of what was happening in the project. Bypassing the hierarchy, one senior technologist eventually wrote a letter to the BBC Trust (the committee with governance and oversight responsibility for the BBC) telling them that they were not being given an accurate picture of the project's true status. According to reports the letter stated that the BBC Trust, the government and other senior parties involved "may have been misled about the true performance of the DMI since it was taken in house".

Sadly the warnings turned out to have merit as the failure to deliver a working system resulted in the project being abandoned in May 2013. Following investigation, Mrs Hodge (the then MP chairing the Public Accounts Committee) described the project as "a terrible shock and clearly completely shambolic" ... "We were told that there were bits of this system that were working, that you were using them. That wasn't true. That just wasn't true." The BBC's Chief Technology Officer was suspended pending an enquiry and £100M was written off.

Contributing factors as reported in the press:

Underestimation of complexity. Ineffective governance structure. Hierarchical organization structure in which accurate flows of information were actively blocked. Failure to conduct an effective tendering process when selecting the original supplier. Lack of contractor oversight. Overstating the benefits of the project. The use of a fixed price contract acted as a barrier that discouraged the BBC from getting too deeply involved in the design stages for fear of triggering change requests thereby nullifying the fixed price.

QUESTIONS

Q.1 What kind of contract has been used for this project? Using the knowledge gained through "Procurement and Contracts Management Unit" explain in detail why was this contract unsuited for the project?

Q.2. What type of contract would you suggest for this project? Justify your reasons explaining the type of contract, its benefits and why it would have suited the Digital Media Initiative Project better?

Q.3. Company ABC is a small community restaurant. As a part of their sustainable initiative they procure organic vegetables from XYZ Farms, which is the country's most popular, high in demand, organic vegetables supplier .

Plot the Supplier Relationship Matrix on behalf of Company ABC as a buyer. Which quadrant would they place XYZ Farms. How should they plan their procurements from XYZ farms?

ACTIVITY

STEP 1: SOURCE PLANNING

1) Identify any two critical materials OR services which your organization procures / could procure externally

2) Step 2: Identify 5 potential suppliers / vendors for each

STEP 2 PLOT THE SUPPLIERS ABOVE INTO THE SUPPLIER CUSTOMER RELATIONSHIP
MATRIX

STEP 3: ANALYSIS AND SUGGESTIONS
Suggest procurement strategies for the above two materials / services based on your analysis.

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M92831946
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Management Theories

Question - choose a product or technology interview five

Question - Choose a product or technology. Interview five consumers who buy that product and ask them what major problems they have with the product (or what major things they dislike about it). Then ask them to describe ...

Case study assignment -case description liang global

Case Study Assignment - Case Description: Liang Global Solutions (LGS) operates in the six New England states. LGS faced an important decision: selecting network software that would maximize functionality, manageability, ...

Df or computer forensics cf laboratory and what actually

(DF) or computer forensics (CF) laboratory and what actually one would find in a lab. Trust me, there are many different artifacts surrounding the DF/CF lab. After you find the article, you are to write a short 1-2 repor ...

Assessment - business research proposalfor this assessment

Assessment - Business Research Proposal For this assessment, students are expected to present a written research proposal that is based on the literature review (Assessment 1) and demonstrates their understanding of busi ...

Identify how protecting sovereign boundaries in regards to

Identify how protecting sovereign boundaries in regards to intellectual property has a positive effect on the GDP . Your answer should be in complete sentences

Benchmark - community teaching plan community

Benchmark - Community Teaching Plan: Community Presentation Note: This is an individual assignment. Based on the feedback offered by the provider, identify the best approach for teaching. Prepare a presentation to accomp ...

In chester barnards view an organisation can be efficient

In Chester Barnard's view, an organisation can be 'efficient' without being 'effective'. Discuss. Discuss your answer, with reference to the key relevant theoretical contributions and academic studies that were reviewed ...

Questionwrite a paper of 1000-1500 words that addresses the

Question: Write a paper of 1,000-1,500 words that addresses the following: 1. Discuss two or three of the major shifts that have occurred in managerial theories and concepts pertaining to the evolution of human resources ...

Questionthe class examined the joint commissions framework

Question: The class examined the Joint Commission's framework for root cause analysis of sentinel incidents in health care organizations. For purposes of this project, a critical incident is a key occurrence, but it is n ...

Three friends tom jerry and mary were having coffee in the

Three friends, Tom, Jerry and Mary were having coffee in the GOSSIP CAFÉ and were discussing their job prospects. Tom told his mates that he has just resigned from his current job because he worked long hours and did not ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As