Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Management Theories Expert

1) The structure that manages projects within the existing organizational structure is __________ organization.

Project

Balanced matrix

Functional

Strong matrix

Weak matrix

2) A series of coordinated, related, multiple projects that continue over extended time intended to achieve a goal is known as a:

Crusade

Program

Campaign

Venture

Strategy

3) Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by:

High overhead

Unforeseen project delays

Imposed project deadlines

Time to market

Incentive contracts

4) The project communication plan contains

Project team vacation schedule

Unapproved change requests

A list of reports to be distributed

An assessment of project risks

Detailed task assignments

5) In which of the following theories does the project group transition from a lower level to a higher level of performance about halfway through the project?

Five Stage Team Development Model

Nominal Group Technique

Synergistic Transition Development Model

Dysfunctional Transition Model

Punctuated Equilibrium Model of Group Development

6) In a resource-constrained project, which of the following is most likely to be changed?

Project quality

The budget

The completion date

7) American project managers have earned a reputation abroad for being very good at understanding technology but not good at understanding:

People

Cultures

Local traditions

Local business practices

Laws

8) _________ organization is a hybrid form in which a horizontal project management structure is overlaid in the normal functional hierarchy.

Functional

Project

Matrix

Balanced

9) The lowest element in the hierarchical breakdown of the WBS is

A work package

A cost account

An object

A lowest sub deliverable

A deliverable

10) A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. What does this report tell you about the project?

We are doing a good job managing the project

We are spending less than we should for the project

We should check to see if all the bills have been paid

We can't be sure how the project is going

11) The project communication plan is usually created by

Team Member

Department Manager

Project Stakeholder

Project Sponsor

Project Manager

12) In which of the following stages is a major portion of the physical and mental project work performed?

Delivering

Planning

Defining

Executing

Conceptualizing

13) If the Project Manager needs additional resources for the project, he/she should seek approval from

Project Stakeholder

Project Sponsor

Project Team

Functional Manager

CEO

14) During the last two phases of a project's life cycle, the most significant source of conflict is:

Costs

Priorities

Schedules

Technical

Procedures

15) The earned value of a project is the:

Total project cost to date

Project cost to date adjusted for project scope changes

Percent of the original budget that has been earned by actual work

Cost incurred minus the planned cost

16) Project leadership is about coping with:

Monitoring results against plans

Formulating plans and objectives

Change

Taking corrective action when necessary

17) The final step in the creation of a Work Breakdown Structure is to

18) Develop the responsibility matrix

Develop the responsibility matrix

Assign the cost account to a manager

Code the WBS for tracking

Assign the work package to a manager

19) The first step in the project control process of the measurement and evaluation of project performance is to

Determine the project objectives

Review the project priority matrix

Analyze the project budget

Set a baseline plan

Determine the project deliverables

20) Two of the biggest challenges involved in managing a virtual project team are:

Time management and developing trust

The language barriers and time management

Developing trust and effective patterns of communication

The language barriers and developing effective patterns of communication

Time management and developing effective patterns of communication

21) The centralized management of projects to ensure that the allocation of resources to projects is directed toward projects that contribute the greatest value to organization goals is known as:

Resource Allocation Optimization

Project Priority Matrix Management

Portfolio Project Management

Project Management Optimization

Project Office Management

22) Sam the project engineer has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of a ______ constraint.

Physical

Scheduling

Technical

Resource

Time

23) Small refinements to the project that eventually build to be major changes are known as:

Continuous improvements

Specification adjustments

Scope creep

Specification refinements

Project erosion

24) Which of the following is considered a project indirect cost

Supervision

Equipment

Materials

Labor

25) From among the following activities, which is the best example of a project?

Producing automobiles

Writing a term paper

Completing a college degree

Processing insurance claims

26) To construct a high-quality, custom home within five months at costs not to exceed $150,000 is best classified as

A deliverable

A limit

An objective

An exclusion

A milestone

27) Audits are least likely to occur

When major milestones are reached

At identified spending level points

During specific stages in the project life cycle

When they are unplanned

28) Project Communication Plans address all the following core questions except:

How will the project team be rewarded?

What information will be communicated?

How will information be communicated?

Who will receive the information?

When will the information be communicated?

29) Communications difficulties because of different languages, social standards, and religious views are examples of which of the following environmental factors?

Cultural

Geographic

Security

Infrastructure

Legal/political

30) Which of the following is considered a project direct cost?

Supervision

Equipment

Interest

Consultants

31) If resources are not adequate to meet peak demands, the resulting reschedule is termed

Project resource adjustment

Resource-constrained scheduling

Bottleneck adjustment

Mandatory leveling

Time-constrained scheduling

32) Which of the following requires more management rather than leadership?

Taking corrective action

Changes in project scope

Breakdowns in coordination between people

MTechnological stalemates

33) In which of the following stages is it determined what the project will entail, when it will be scheduled, whom it will benefit, and what the budget will be?

Defining

Executing

Delivering

Conceptualizing

Planning

34) In reviewing the project plan, Susan sees that the first prototype is due by October 12. This would be best classified as a

Critical goal

Project objective

Limit item

Milestone

Project target

35) The most common response for meeting unattainable deadlines is to:

Implement the fast-tracking system

Fire the project manager

Hire more people

Shift to the critical chain

Reduce or scale back the scope of the project

36) The process of forecasting or approximating the time and cost of completing project deliverables is called

Planning

Predicting

Budgeting

Guesstimating

Estimating

37) A typical expectation in actual practice is that estimates should have a probability of being met ______ of the time.

95%

80%

98%

100%

90%

38) The last step in the Change Control Management process is

Negotiate and resolve conflicts

Formally disapprove changes

Track all changes that are to be implemented

Change the project schedule

Lodge a complaint

39) The most common response for meeting unattainable deadlines is to:

Reduce or scale back the scope of the project

Implement the fast-tracking system

Fire the project manager

Hire more people

Shift to the critical chain

40) In which of the following stages are project objectives established, teams formed, and major responsibilities assigned?

Defining

Delivering

Executing

Conceptualizing

Planning

41) Needs for a project could include telecommunications, transportation, power, and availability of technically skilled talent. This is an example of which of the following environmental factors?

Cultural

Economic

Geographic

Infrastructure

Legal/political

42) The method most frequently used in measuring project progress is the

75/25 percent rule

Percent complete rule

0/100 percent rule

50/50 percent rule

25/75 percent rule

43) A good benchmark to use as a time limit for conducting a project audit is

One week

Two weeks

One month

One day

Two months

44) Corrective actions that should take place would typically appear in the _____ section of the audit report.

Strategic objectives

Lessons learned

Analysis

Classification of project

Recommendations

45) The person responsible for tracking approved changes to the project is

Project Manager

Project Requestor

Project Team Member

Project Stakeholder

Project Sponsor

46) The project is running behind schedule, the best thing for the project manager to do is

Take corrective action

Apply for a transfer

Produce a Gantt Chart

Hire more resources

47) The method used to collect information to use through all phases of the project life cycle is called

Work breakdown structure

Organization breakdown structure

Priority matrix

Responsibility matrix

Work package

48) Which of the following is the easiest method for shortening project time?

Subcontract work

Reduce project scope

Schedule overtime

Reduce the quality

Assigning additional staff and equipment

49) In which of the following is the balance of authority strongly in favor of the functional managers?

Balanced matrix

Weak

Strong matrix

Strong

50) Which of the following is commonly associated with high-performing project teams?

A degree of competition among team members is encouraged

Roles and specific responsibilities are well-defined

Mistakes are viewed as opportunities for learning

Risk taking is controlled and not allowed to jeopardize the overall project

51) The first step of project scope definition is to

Define the overall objective to meet the customer's needs

Meet with team members

Analyze the current budget plan

Select team members

Analyze the strategic plan

52) In reviewing the project plan, Susan sees that the first prototype is due by October 12. This would be best classified as a

Limit item

Critical goal

Project objective

Project target

Milestone

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M91913055
  • Price:- $55

Priced at Now at $55, Verified Solution

Have any Question?


Related Questions in Management Theories

What is the result of a price ceiling and why do some

What is the result of a price ceiling? And why do some consumers tend to favor price ceilings and others tend to oppose it?

Journal empowering your peopleinstructionsama style with

Journal: Empowering Your People Instructions: AMA Style with references! Journal entries are private between you and the instructor. In this course, journals are low stakes opportunities to submit small portions of your ...

Final reflection-preparing for final assignmentthroughout

Final Reflection- Preparing for Final Assignment: Throughout the course, numerous topics on healthcare management have been discussed. Reflecting on the different discussions, readings, assignments, and your previous cou ...

Identify how protecting sovereign boundaries in regards to

Identify how protecting sovereign boundaries in regards to intellectual property has a positive effect on the GDP . Your answer should be in complete sentences

Assignment -for this assignment analyze and discuss your

Assignment - For this assignment, analyze and discuss your personal leadership style. Based on your experiences, current readings, work experience, education, and use of self-assessment instruments describe what you thin ...

Think about one effective and one ineffective leader who

Think about one effective and one ineffective leader who you have encountered. Determine how each leader was effective or ineffective in his or her leadership styles and explain your reasoning with support from sources a ...

Cnsider the binomial distribution where n 11 and p

Consider the binomial distribution where n = 11 and p = 0.05. Find the mean and standard deviation of this binomial distribution. The customers at a local appliance store are polled as they leave the store. Each is asked ...

Business research assignments -assessment 1 - literature

Business Research Assignments - Assessment 1 - Literature Review (2000 to 2500 words) For this assessment, students are expected to demonstrate their understanding of the extant, academic literature related to an approve ...

Assessment - business research proposalfor this assessment

Assessment - Business Research Proposal For this assessment, students are expected to present a written research proposal that is based on the literature review (Assessment 1) and demonstrates their understanding of busi ...

Assignmentlearning outcome recognize the impact of

Assignment Learning Outcome: Recognize the impact of organizational culture on shaping values, attitudes and behavior. Case Study: Foundations of Individual Behavior Differing Perceptions at Clarkston Industries Susan Ha ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As