1. The Procurement Management Plan although part of the PMP would start to be developed in which stage of the project life cycle?

A. Initiation

B. Planning

C. Executing

D. Monitor & Control

2. Disadvantages of outsourcing project work may include all of these except:

A. increased conflict

B. coordination breakdowns

C. increased costs

D. loss of control

3. Which of the following are valid contract types?

A. Build, Own, Operate, Transfer (BOOT)

B. Build, Own, Operate (BOO)

C. Build, Operate, Transfer (BOT).

D. All the given answers are correct.

4. Which of these is not a valid cost reimbursable contract type?

A. Cost plus flexible fee (CPFF) contracts

B. Cost plus incentive fee (CPIF) contracts

C. Cost plus award fee (CPAF) contracts

D. Cost plus fixed fee (CPFF) contracts

5. The driving motive for increasing the use of outsourcing on projects is:

A. reducing the trade deficit

B. reducing costs

C. improving international sales

D. making products more international in design

6. Recent outsourcing trends have shown an increasing emphasis on the suppliers for all of these except:

A. further cost reductions

B. increased quality of work performed

C. increased ability to collaborate

D. increased ability to work together

7. Which of these is not a key to successful partnering relationships?

A. Mutual trust

B. Jointly shared risk

C. Total company involvement

D. Independent project teams

8. Best practices in outsourcing project work include all of these except:

A. training and teambuilding activities

B. well established conflict management processes

C. frequent reviews and status updates

D. All the given answers are correct.

9. Best practices in outsourcing project work include all of these except:

A. training and teambuilding activities

B. well established conflict management processes

C. frequent reviews and status updates

D. All the given answers are correct.

10. To avoid problems with schedules and deadlines you should:

A. develop detailed schedules

B. hold frequent status reviews

C. add a penalty clause to the contract

D. hold frequent conversations with the outsourcer

11. How is risk shared in partnerships?

A. One party only

B. 50/50

C. With the new partnership entity

D. All the given answers are correct.

12. Which of these is not one of the key points of principled negotiation?

A. Use objective criteria when possible

B. Be honest and forthright

C. Focus on interests, not positions

D. Invent options for mutual gain

13. Which is not one of the six stages of contract negotiation?

A. Offer and acceptance (agreement)

B. Intention to create legal relations

C. Engagement

D. Consideration

14. Which of these is not one of the elements of good negotiation?

A. Conflict on a project can be good

B. Negotiation is not a contest

C. Seek first to understand, then to be understood

D. All the given answers are correct.

15. Which of the following is reflected in the saying ‘Seek first to understand, then to be understood'?

A. Separate people from the problem

B. Be honest

C. Focus on interests, not positions

D. Invent options for mutual gain

16. A project manager should adopt the preferred suppliers of the parent organisation.

True False

17. A firm fixed price contract offers the buyer less risk than the seller?

True False

18. The cost plus fixed fee (CPFF) contract is where a fixed fee is agreed upon for an estimated amount of work (determined during project estimating). This fee, together with agreed ‘allowable costs', are subsequently billed back to the supplier.

True False

19. Dispute arrangements should be agreed but not documented in the contract?

True False

20. Sub-contracting arrangements should be agreed and documented in the contract?

True False

21. In partnering, access to each other's organisation resources is available.

True False

22. It is a good idea to add a penalty clause to an outsourcing agreement because deadlines are often taken as a suggestion rather than a commitment.

True False

23. List 12 contract/tender selection criteria that would be vital to consider in any contaract/tender selection.

24. Describe the key activities carried out in the Initiation stage of the project life cycle from a procurement perspective.

25. Describe the key activities carried out in the Planning stage of the project life cycle from a procurement perspective.

26. Describe the key activities carried out in the Execution stage of the project life cycle from a procurement perspective.

27. Describe the key activities carried out in the Closing stage of the project life cycle from a procurement perspective.

28. Identify the four advantages to outsourcing project work.

29. Identify the disadvantages of outsourcing project work.

Management Theories, Management Studies

  • Category:- Management Theories
  • Reference No.:- M92274000

Have any Question?


Related Questions in Management Theories

Firm a has been dealing in baby food products for the past

Firm A has been dealing in baby food products for the past 10 years and enjoys a good market share. Suppose a new firm enters the market to capitalize on the increasing demand for such products. However, the products of ...

Assume that a perfectly competitive firm has the following

Assume that a perfectly competitive firm has the following revenue and cost functions: TC= 5625 +5Q + 0.01Q^2 AVC=5 + 0.01Q MC=5 + 0.02Q TR=20Q A) what is the level of output that maximizes profits, if any? Compute profi ...

Seek out at least three individuals within your sphere of

Seek out at least three individuals within your sphere of influence and ask the following: What does workplace stress feel like to you? What activities or actions do you or your organization initiate to reduce workplace ...

Journal empowering your peopleinstructionsama style with

Journal: Empowering Your People Instructions: AMA Style with references! Journal entries are private between you and the instructor. In this course, journals are low stakes opportunities to submit small portions of your ...

Strategic information systems assignment - literature

STRATEGIC INFORMATION SYSTEMS ASSIGNMENT - Literature Review Write a literature review of NOT more than 2000 words. The review should demonstrate that the student has thoroughly researched their topic. Students should us ...

Tasks1select any four of the following fundamental

Tasks: 1. Select any four of the following fundamental theories: o The Ten Commandments o The Justification of Human Rights o Utilitarianism o Aristotelian Ethics o International Ethics Standards for Business o Distribut ...

Styles of leadershipinstructionsama style with

Styles of Leadership Instructions AMA style with references When preparing for your discussion post on this case, it is recommended that you read through it several times. Read through it the first time to familiarize yo ...

What do you recommend that a company do to prevent andor

What do you recommend that a company do to prevent and/or solve subscriber uncollectable issues?

Assignmentlearning outcome recognize the impact of

Assignment Learning Outcome: Recognize the impact of organizational culture on shaping values, attitudes and behavior. Case Study: Foundations of Individual Behavior Differing Perceptions at Clarkston Industries Susan Ha ...

Archetypes in actionsenge ross smith roberts amp kleiner

Archetypes in Action Senge, Ross, Smith, Roberts, & Kleiner (1994) noted: At its broadest level, systems thinking encompasses a large and fairly amorphous body of methods, tools, and principles, all oriented to looking a ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As