You have just determined the actual number of workstations that will be used on an assembly line to be 8 using the assembly-line balancing procedure. The cycle time of the line is 600 seconds and the sum of all that taks required on the line is 60 minutes. Which of the following is the correct value for the resulting line's efficiency?

a) 0.00125
b) 0.5
c) 0.650
d) 0.750
e) 0.835

 

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M9356942

Have any Question?


Related Questions in Project Management

What is the current state or condition of information

What is the current state or condition of Information Technology Project Management? What are the challenges and complexities faces by many IT Project Managers of today?

Annotated bibliographythis table lists criteria and

Annotated Bibliography This table lists criteria and criteria group name in the first column. The first row lists level names and includes scores if the rubric uses a numeric scoring method. Criteria Exemplary Competent ...

Mikes tees a relatively large company that prints t-shirts

Mike's Tees, a relatively large company that prints T-shirts, is developing a system that allows customers to upload their image files on a server and have them printed on T-shirts. The project was drafted and planned to ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Reflect on kotters 2007 steps for establishing a strategic

Reflect on Kotter's (2007) steps for establishing a strategic vision and buy-in for change. Describe how that framework can be applied to your strategic initiatives withinproject. Provide thoughts on how this could impro ...

Project proposal -project - plan for implementing spc for

PROJECT PROPOSAL - Project - Plan for implementing SPC for improvement Introduction/aims/objectives - 200 words max Indicative literature review - 500 words max Indicative research methodology - 500 words max An idea to ...

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Read the article - project management time amp cost

Read the article - Project Management Time & Cost Estimation Techniques: An Overview by Sid Kemp Using this article and other resources that you locate, write a one page paper answering the following points: - Explain wh ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As