You are completing a software development project. This project is expected to add SIX new features to a popular software program you sell to customers. The projected cost for the project is $100,000 and the development is expected to take 5 weeks. At the end of the second week, you spent $17,500 per new software feature and you completed the development of two new features. You are about to start the development of the third new software feature. Based on this information, fill in the table below:

BAC

PV

EV

AC

CV = EV-AC

SV = EV - PV

CPI = EV/AC

SPI = EV/PV

EAC = BAC/CPI

ETC = EAC-AC

VAC = BAC-EAC

TCPI (Cost) = (BAC-EV)/(BAC-AC)

Based on the values you computed, is the project ahead of schedule or behind schedule? Will the project be completed under budget or will it exceed the budget?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92847066
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Project Management

You are recently assigned to manage an effort to upgrade

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your compan ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Mikes tees a relatively large company that prints t-shirts

Mike's Tees, a relatively large company that prints T-shirts, is developing a system that allows customers to upload their image files on a server and have them printed on T-shirts. The project was drafted and planned to ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

What are the advantages and disadvantages of cost of poor

What are the advantages and disadvantages of Cost of Poor Quality (COPQ)?

Assignment 1 the core values and principlesplease have the

Assignment 1: The Core Values and Principles Please have the following titles and include content as per assignment instructions under each paragraph: History of Agile project management. Philosophy and purpose of Agile ...

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

What is the current state or condition of information

What is the current state or condition of Information Technology Project Management? What are the challenges and complexities faces by many IT Project Managers of today?

As a project manager answer these questions1 a how does the

As a project manager answer these questions, 1) a. How does the weighted scoring approach avoid the drawbacks of the NPV approach? b. Can the two approaches be combined? if so How? How are you going to apply this piece o ...

What is fast tracking and its impact on the project as it

What is fast tracking and its impact on the project as it relates to project management

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As