You are completing a software development project. This project is expected to add SIX new features to a popular software program you sell to customers. The projected cost for the project is $100,000 and the development is expected to take 5 weeks. At the end of the second week, you spent $17,500 per new software feature and you completed the development of two new features. You are about to start the development of the third new software feature. Based on this information, fill in the table below:

BAC

PV

EV

AC

CV = EV-AC

SV = EV - PV

CPI = EV/AC

SPI = EV/PV

EAC = BAC/CPI

ETC = EAC-AC

VAC = BAC-EAC

TCPI (Cost) = (BAC-EV)/(BAC-AC)

Based on the values you computed, is the project ahead of schedule or behind schedule? Will the project be completed under budget or will it exceed the budget?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92786892
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Project Management

Project proposal -project - plan for implementing spc for

PROJECT PROPOSAL - Project - Plan for implementing SPC for improvement Introduction/aims/objectives - 200 words max Indicative literature review - 500 words max Indicative research methodology - 500 words max An idea to ...

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

Check all of the following that arenbsptrue for top-down

Check all of the following that are  true for top-down estimates (when being compared with bottom-up estimates). Make sure your answer reflects what is correct for  Top-Down Estimates .  Lower cost to create estimate Hig ...

Define a strategic information system give two examples of

Define a strategic information system. Give two examples of these systems

1 what are some benefits and values of scheduling software

1) What are some benefits and values of scheduling software in a project schedule?

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Annotated bibliographythis table lists criteria and

Annotated Bibliography This table lists criteria and criteria group name in the first column. The first row lists level names and includes scores if the rubric uses a numeric scoring method. Criteria Exemplary Competent ...

What are the advantages and disadvantages of cost of poor

What are the advantages and disadvantages of Cost of Poor Quality (COPQ)?

As a project manager answer these questions1 a how does the

As a project manager answer these questions, 1) a. How does the weighted scoring approach avoid the drawbacks of the NPV approach? b. Can the two approaches be combined? if so How? How are you going to apply this piece o ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As