When must planned order release(s) take place for material requirements planning (MRP) data given below? Quantity = 60; Lead Time = 3 weeks.

Period (week) 1 2 3 4 5

Requirements 80 -- 90 -- 90
Scheduled Receipts 60
Projected Stock balance 190
Planned Order Release

A - Week 1
B - Week 2
C - Week 3
D - Week 4

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M933513

Have any Question? 

Related Questions in Project Management

1 write short notes ona role of project sponsorsb

1. Write short notes on: a. Role of project sponsors b. Importance of project budget c. Debt financing d. Financial feasibility of a project 2. Describe the Engineering, Procurement Construction (EPC) contract. 3. Explai ...

During this discussion talk about and examine the processes

During this discussion, talk about and examine the process(es) of collecting information security measures, how often do they need to be collected, what are the downsides of collecting and reporting the measures too freq ...

Carlton speciality plc is a small family owned firm that

Carlton Speciality PLC is a small family owned firm that manufactures custom made furniture and uses job costing system. The company does not have computerised system and thus maintains all accounting records on hard cop ...

It project management techniques assignmenttask - team

IT Project Management Techniques Assignment Task - Team Project Management Plan. Objectives - This assessment task relates to the following course objectives: Identify traditional and agile approaches and lifecycles for ...

Project deliverable project planthis assignment consists of

Project Deliverable: Project Plan This assignment consists of three sections: a written project plan, revised business requirements document, project plan PowerPoint presentation, and a finalized project plan. You must s ...

Project risk management - assignmentquantitative risk

PROJECT RISK MANAGEMENT - ASSIGNMENT QUANTITATIVE RISK ANALYSIS - Monte Carlo Simulation Learning Objective of Assignment - To apply risk analysis quantitative techniques to projects. Select a project. Can be from your w ...

Assessment 1 - project workpart aoverviewyou are required

ASSESSMENT 1 - PROJECT WORK Part A Overview You are required to develop a project management plans, for given scenarios. These project plans requires you to: - Implement start-up activities through updating and confirmin ...

Assignment overviewthe development and implementation of a

Assignment Overview The development and implementation of a Project Management Office (PMO) in an organisation offers many and varied benefits to an organisation and so the popularity of PMOs in the contemporary project ...

Your ceo is a visionary who wants you to transform the way

Your CEO is a visionary who wants you to transform the way the company conducts business. She is fascinated by computer software for project management and requires that you conduct a SWOT analysis of this service in rel ...

As an hr manager discuss ways you can promote a wellness

AS an HR manager, discuss ways you can promote a wellness program for all employees and encourage them to join? What incentives can you use to encourage participation without making it mandatory to join? What are the ben ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

A cola-dispensing machine is set to dispense 9 ounces of

A cola-dispensing machine is set to dispense 9 ounces of cola per cup, with a standard deviation of 1.0 ounce. The manuf

What is marketingbullwhat is marketing think back to your

What is Marketing? • "What is marketing"? Think back to your impressions before you started this class versus how you

Question -your client david smith runs a small it

QUESTION - Your client, David Smith runs a small IT consulting business specialising in computer software and techno

Inspection of a random sample of 22 aircraft showed that 15

Inspection of a random sample of 22 aircraft showed that 15 needed repairs to fix a wiring problem that might compromise

Effective hrmquestionhow can an effective hrm system help

Effective HRM Question How can an effective HRM system help facilitate the achievement of an organization's strate