IT Project Management Calculations

Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following:

PV = $120,000
EV = $100,000
AC = $90,000

A. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

B. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

C. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M9218794

Have any Question?


Related Questions in Project Management

Project investment analysis assignment -the aim of this

PROJECT INVESTMENT ANALYSIS ASSIGNMENT - The aim of this project is to introduce participants to concepts of Financial Feasibility Modelling and the use of spreadsheets for feasibility exercises. Assume that you have bee ...

Discuss the different approaches to developing either a

Discuss the different approaches to developing either a Product Breakdown Structure (PBS) OR a Work Breakdown Structure (WBS).

Part -1 define project and develop planperformance

Part -1 Define project and develop plan Performance objective Candidates will demonstrate knowledge and skills required to define projects and develop project plans. Assessment description Using the workplace scenario in ...

42908 assessment task - project proposal1 executive summary

42908 Assessment Task - Project Proposal 1. Executive Summary - Brief overview of project, main aim of project, potential findings and conclusions. 2. Introduction - Presents general project area, relevance of project, s ...

You are recently assigned to manage an effort to upgrade

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your compan ...

Leading lean projects assessment case study - continuous

Leading Lean Projects Assessment Case study - Continuous Improvement Introduction - Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the t ...

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

Mikes tees a relatively large company that prints t-shirts

Mike's Tees, a relatively large company that prints T-shirts, is developing a system that allows customers to upload their image files on a server and have them printed on T-shirts. The project was drafted and planned to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

As a project manager answer these questions1 a how does the

As a project manager answer these questions, 1) a. How does the weighted scoring approach avoid the drawbacks of the NPV approach? b. Can the two approaches be combined? if so How? How are you going to apply this piece o ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As