Attempt all the problems.
Section-A
problem1)(a) What are the criteria for IT project selection? describe.
(b) Describe the different points that must be kept in mind while closing a project
problem2)(a) What is project scope management? describe different processes involved in project scope management.
(b) How could you control changes to project schedule?
problem3)(a) describe the seven processes of project integration management.
(b) How IT project differs from other project? describe the different steps that require to be considered for handling an IT project.
problem4)(a) What are main attributes of a project?
(b) How do you define success or failure of a project?
Section-B
Case Study
The following data are available for a maintenance project:
Activity Optimistic time (in days) Pessimistic time (in days) Most likely time (in days)
1-2 1 3 2
1-4 4 6 5
1-3 4 6 5
2-6 2 4 3
2-4 1 3 2
3-4 2 4 3
3-5 7 15 9
4-6 4 6 5
4-7 6 14 10
4-5 1 3 2
5-7 2 4 3
6-7 6 14 10
problem5) Case problems:
a) Draw the arrow diagram for this project and determine the critical path and its associated time.
b) What is the expected time for 68, 95 and 99 percent completion limits?