Cynthia Gao, procurement manager for Wedlock Engineered Products in Buffalo, New York, was reviewing a proposal recommending that the company change suppliers for a critical raw material. It was June the 3rd, and Cynthia needed to decide before the end of the day how she would respond to the proposal.

WEDLOCK ENGINEERED PRODUCTS

Wedlock Engineered Products (Wedlock) manufactured and distributed hydraulic, power-assisted, air-powered, and standard mechanical dock levelers, and dock seals and shelters, and vehicle restraints. Wedlock had profits 294 Purchasing and Supply Management of $50 million on sales of $450 million in the most recent fiscal year ending December 31. The company had enjoyed double-digit growth over the previous decade, supported mainly through an aggressive acquisition strategy. Wedlock’s growth masked cost pressures the company was facing in its key markets. The company’s annual report indicated that financial results were lower than expected due to price erosion. In February, the CEO, Dmitry Barsukov, announced a corporate cost-reduction initiative aimed at improving the company’s competitive position. As part of the announcement, Barsukov specifically mentioned “opportunities for supply chain savings through coordination of purchasing between operating units and divisions.” The Buffalo plant manufactured hydraulic dock levelers that were installed in shipping and receiving areas in manufacturing facilities, distribution centers, retail operations, and other facilities required to accommodate loading and unloading of highway transport trailers. It produced a standard product that was sold in the replacement and new construction markets under the Sloan Leveler brand. The Wedlock plant in Cleveland, Ohio, also manufactured hydraulic levelers, under the brand name Cole Dock Levelers. The Cole line of levelers targeted the customized market, for customers with unique material handling requirements.

PURCHASING AT THE BUFFALO PLANT

Cynthia Gao, along with Garett MacDonald, buyer, and Adam McEniry, materials planner, comprised the procurement group at the Wedlock plant in Buffalo. Total purchases were $23 million. Cynthia worked closely with Robert Scobie, her counterpart at the Cleveland plant, to coordinate purchases and identify opportunities for costs savings. The Cleveland plant was similar in size to the Buffalo plant, with approximately $25 million in annual purchases. Cynthia and Robert had committed to savings of $1.5 million in the current fiscal year as part of the corporate cost-reduction initiative. They had documented approximately $500,000 so far, measured by year-over-year price reductions from suppliers and based on forecasted annual usage.

STEEL TUBING

The Buffalo and Cleveland plants purchased 3-inch steel tube with a combined total value of $1.1 million annually. The tubing was used on the loading dock platform to support the hinge connected to the lip of the platform that allowed it to lay flat or unfold, in order to connect or disconnect from the transport trailer. The tubing was required to meet specific metallurgical standards or else the tubing would warp or crack, causing the loading dock to malfunction. The current supplier for 3-inch tubing was Marandi Steel (Marandi). Located near Buffalo, Marandi distributed a wide range of carbon, stainless, alloy, and aluminum tubing; pipe products in round, square, and rectangular shapes; and steel plate to manufacturing companies in the eastern United States and Canada. Marandi had been a supplier to the Wedlock Buffalo plant for approximately 15 years and provided excellent service. Cynthia had a strong working relationship with the general manager at Marandi and could recount several occasions when they reacted quickly to material shortages at the Buffalo plant that helped keep production going. Marandi currently supplied several products, including tubular steel, shapes, and plate, to both the Wedlock Buffalo and Cleveland plants. The supply arrangement with Marandi to the Buffalo plant included just-in-time delivery arrangements, which helped to keep inventory levels at a minimum. Total annual purchases from the supplier were approximately $3 million for the Buffalo plant and $2.5 million for the Cleveland plant. In order to test the pricing for 3-inch tubing, Robert Scobie issued a request for quotations (RFQ) the previous month from several steel tubing distributors, including Marandi. The RFQ indicated the expected term of the contract would be two years and include 100 percent of the requirements for both the Buffalo and Cleveland plants. The two lowest quotes were from Vergis Tubing (Vergis), located in Erie Pennsylvania, and Marandi. The quote submitted by Vergis represented an annual cost savings of approximately $24,000 compared to the incumbent supplier.

REVIEWING OPTIONS

Robert felt that Vergis should be awarded the contract to supply 3-inch tubing for the Buffalo and Cleveland plants and was urging Cynthia to accept the proposal. However, Cynthia had concerns. Vergis had attempted unsuccessfully on several other occasions to secure business from Wedlock, and she was worried that Vergis did not have any history with either the Buffalo or Cleveland plants. Delivery and quality performance for 3-inch tube was critical for the Buffalo plant, and the performance of Marandi in these areas had been outstanding. A check of Chapter 10 Price 295 Vergis’s references found that they had a good reputation and there were no problems uncovered. Cynthia was also concerned about the effect of abandoning a long-standing relationship, which might have other cost implications and jeopardize service provided by Marandi. Marandi supplied a number of other products to the Buffalo plant, and Cynthia wondered how awarding the 3-inch tube contract to Vergis would affect the relationship with Marandi. Robert was expecting a decision from Cynthia the following morning regarding which supplier she felt should be awarded the contract for 3-inch tubing. Cynthia knew that she would need strong arguments if she decided not to support his recommendation to switch to Vergis.

1. If you switch to Vergis for the 3-inch tubes, how will that affect your relationship with Marandi for the rest of your business with them?

2. Is using an RFQ the right approach in this situation?

3. As Cynthia Gao, what recommendation would you make to Robert Scobie regarding supply for the 3-inch tubes?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93107540

Have any Question?


Related Questions in Operation Management

Mr ahmed wants to open a small edu park for children with

Mr. Ahmed wants to open a small Edu park for children with special needs so that the Edu park will not only provide special education and training for such children but also give some fun related games where such childre ...

Many companies such as intel microsoft and gap inc have

Many companies, such as Intel, Microsoft, and Gap Inc., have revamped their performance management systems to eliminate ratings they feel demoralize and threaten employees, take too long for managers to complete, and con ...

1 juan is a highly qualified biomedical researcher having

1. Juan is a highly qualified biomedical researcher. Having recently completed his education, he applies to work at a pharmaceutical company which is renowned for its fast paced innovation and aggressive growth policy. W ...

Your firm designs manufactures and markets childrenrsquos

Your firm designs, manufactures, and markets children’s toys for sale in the U.S. Almost 90% of your production is done in China. During the 1990s, U.S. relations with China improved. Even though there were many disagree ...

1 which of the following is not an argument for strategic

1. Which of the following is not an argument for strategic consistency? Strategic change can be expensive. Strategic changes usually fail in the long run. Consumer confusion may result from strategic change even then the ...

Promptyour main post should include the vision your summary

Prompt: Your main post should include the vision, your summary data, the productivity findings, and the customer service standards you wish to achieve. This paper should be cohesive and thorough for maximum points. Our v ...

1 list and explain the key benefits of demand-driven supply

1. List and explain the key benefits of demand-driven supply networks. 2. Draw the e-business model and explain how the e-procurement module streamline and automate the process with the suppliers and other business partn ...

1 what are the two ways work center can be loaded what are

1. What are the two ways work center can be loaded? What are the two techniques in loading? 2. Name five priority sequencing rules. Explain how each works to assign jobs 3. Explain the term flow time and lateness 4. What ...

1 pick a habit that you have discuss specific skills you

1. Pick a habit that you have. Discuss specific skills you use from this habit that enable you to achieve a successful outcome. 2. According to Theodore Levitt, what are the three assumptions that favor the pursuit of a ...

Evaluating your businessthe required of the question

Evaluating Your Business? the required of the question above -You are working for a fashion company as an E-Commerce consultant. -Suppose you have been asked to design an online store for the company. -How do you promote ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As