The Family Planning Research Center of Nigeria

Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria's Over-The-River Province, was assigned the task of organizing and training five teams of field workers as part of a large project to demonstrate acceptance of a new method of birth control. These workers had already had training in family planning education, but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accommodations for the participants.

Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, the necessary sequences, and the time they would require. Their results appear in Table 1.

Table 1 The Family Planning Research Center

 

ACTIVITY

MUST FOLLOW

TIME (IN DAYS)

STAFFING NEEDED

A

Identify faculty and their schedules

--

5

2

B.

Arrange transport to base

--

7

3

C.

Identify and collect training materials

--

5

2

D.

Make accommodations

A

3

1

E.

Identify team

A

7

4

F.

Bring in team

B, E

2

1

G.

Transport faculty to base

A, B

3

2

H.

Print program material

C

10

6

I.

Deliver program materials

H

7

3

J.

Train team

D, F, G, I

15

0

K.

Do fieldwork

J

30

0

Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the times needed given in Table 1. They came to 94 days. "An impossible task then," he noted. "No," Dr. Watage replied, "some of these tasks can go forward in parallel." "Be careful though," warned Mr. Oglagadu, the chief nurse, "there aren't that many of us to go around. There are only 10 of us in this office."

"I can check whether we have enough heads and hands, once I have tentatively scheduled the activities," Dr. Watage responded. "If the schedule is too tight, I have permission from the Pathminder Fund to spend some money to speed it up, just so long as I can prove that it can be done at the least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed times that we planned. Also, here are the costs and times if we shorten them to an absolute minimum." Those data are in Table 2.

Table 2 The Family Planning Research Center

 

 

Normal

Minimum

Average Cost
Per Day Saved ($)

 

Activity

Time

Cost($)

Time

Cost ($)

 

A.

Identify faculty

5

400

2

700

100

B.

Arrange transport

7

1,000

4

1,450

150

C.

Identify materials

5

400

3

500

50

D.

Make accommodations

3

2,500

1

3,000

250

E.

Identify team

7

400

4

850

150

F.

Bring team in

2

1,000

1

2,000

1,000

G.

Transport faculty

3

1,500

2

2,000

500

H.

Print material

10

3,000

6

4,000

250

I.

Deliver materials

7

200

2

600

80

J.

Train team

15

5,000

10

7,000

400

K.

Do fieldwork

30

10,000

20

14,000

400

Source: Professor Curtis P. McLaughlin, Kenan-Flagler Business School, University of North Carolina at Chapel Hill.

Final Project Tasks

  1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required network of tasks, and define the critical path. What is the length of the project without crashing?
  2. At this point, can the project be done given the constraint of having only 10 persons?
  3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve the schedule objective? How can he prove to the Pathminder Fund that this is the minimum cost alternative?
  4. Utilizing the concepts from this course, prepare the project plan based on the information on this case study.  The topics from this class are listed below.  Please incorporate each bullet item into your plan.
  • Define Project Planning
  • Develop the Project Plan
  • Scope Planning
  • Scope Definition
  • Creating the Work Breakdown Schedule (WBS)
  • Activity Definition
  • Activity Sequencing
  • Resource Estimating
  • Duration Estimating
  • Schedule Development and
  • Cost Estimating
  • Cost Budgeting
  • Quality Planning
  • Human Resource Planning
  • Communications Planning
  • Risk Planning and
  • Risk Identification
  • Qualitative Analysis
  • Quantitative Analysis
  • Plan Purchases and Acquisitions
  • Plan Contracting

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91564887
  • Price:- $70

Priced at Now at $70, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As