THE ESTIMATING PROBLEM

Barbara just received the good news: She was assigned as the project manager for a project that her company won as part of competitive bidding. Whenever a request for proposal (RFP) comes into Barbara's company, a committee composed mainly of senior managers reviews the RFP. If the decision is made to bid on the job, the RFP is turned over to the Proposal Department. Part of the Proposal Department is an estimating group that is responsible for estimating all work.

If the estimating group has no previous history concerning some of the deliverables or work packages and is unsure about the time and cost for the work, the estimating team will then ask the functional managers for assistance with estimating.

Project managers like Barbara do not often participate in the bidding process. Usually, their first knowledge about the project comes after the contract is awarded to their company and they are assigned as the project manager.

Some project managers are highly optimistic and trust the estimates that were submitted in the bid implicitly unless, of course, a significant span of time has elapsed between the date of submittal of the proposal and the final contract award date. Barbara, however, is somewhat pessimistic. She believes that accepting the estimates as they were submitted in the proposal is like playing Russian roulette. As such, Barbara prefers to review the estimates.

One of the most critical work packages in the project was estimated at twelve weeks using one grade 7 employee full time. Barbara had performed this task on previous projects and it required one person full time for fourteen weeks. Barbara asked the estimating group how they arrived at this estimate. The estimating group responded that they used the three-point estimate where the optimistic time was four weeks, the most likely time was thirteen weeks, and the pessimistic time was sixteen weeks.

Barbara believed that the three-point estimate was way off of the mark. The only way that this work package could ever be completed in four weeks would be for a very small project nowhere near the complexity of Barbara's project. Therefore, the estimating group was not
considering any complexity factors when using the three-point estimate.

Had the estimating group used the triangular distribution where each of the three estimates had an equal likelihood of occurrence, the final estimate would have been thirteen weeks. This was closer to the fourteen weeks that Barbara thought the work package would take. While a difference of 1 week seems small, it could have a serious impact on Barbara's project and incur penalties for late delivery.

Barbara was now still confused and decided to talk to Peter, the employee that was assigned to do this task. Barbara had worked with Peter on previous projects. Peter was a grade 9 employee and considered to be an expert in this work package. As part of the discussions with Barbara, Peter made the following comments:

I have seen estimating data bases that include this type of work package and they all estimate the work package at about 14 weeks. I do not understand why our estimating group prefers to use the three point estimate.

"Does the typical data base account for project complexity when considering the estimates?"asked Barbara. Peter responded:

Some data bases have techniques for considering complexity, but mostly they just assume an average complexity level. When complexity is important, as it is in our project, analogy estimating would be better. Using analogy estimating and comparing the complexity of the work package on this project to the similar works packages I have completed, I would say that 16-17 weeks is closer to reality, and let's hope I do not get removed from the project to put out a fire somewhere else in the company. That would be terrible. It is impossible for me to get it done in 12 weeks. And adding more people to this work package will not shorten the schedule. It may even make it worse.

Barbara then asked Peter one more question:

Peter, you are a grade 9 and considered as the subject matter expert. If a grade 7 had been assigned, as the estimating group had said, how long would it have taken the grade 7 to do the job?

"Probably about 20 weeks or so," responded Peter.

QUESTIONS

1. How many different estimating techniques were discussed in the case?

2. If each estimate is different, how does a project manager decide that one estimate is better than another?

3. If you were the project manager, which estimate would you use?

Management Information System, Management Studies

  • Category:- Management Information System
  • Reference No.:- M92566070

Have any Question?


Related Questions in Management Information System

Project title security lapses and data breaches an

Project Title: "Security Lapses and Data Breaches: An Examination of the Failures to Protect Business Data and their Consequences" Instruction of creating the Background: Background information expands upon the key point ...

Research histogram and its use then post a description of

Research Histogram, and its use, then post a description of Histogram, and describe it in detail-explaining its purpose and how it works. Give your opinion on when it would be appropriate to use this tool in an IT settin ...

Ethics and information managementusing university library

Ethics and Information Management: Using University library and/or other sources, read at least four (4) academically reviewed articles on the ethical issues that may arise in information management. 1. Write a comparati ...

Please discuss what you believe is the relationship of ea

Please discuss what you believe is the relationship of EA and enterprise systems. In particular, please discuss: 1. How enterprise architecture and enterprise systems influence, support, and enable an organization's abil ...

Instructionsyou have just been hired as a compliance

Instructions You have just been hired as a compliance officer for your healthcare organization, and you have discovered that the food services department of the organization is not in compliance with state food safety re ...

Instructionschoose one of the scenarios below a or b to

Instructions Choose one of the scenarios below (A or B) to complete the assignment. Scenario A You are the business owner of a local small engine repair shop, and you have been thinking about implementing a knowledge man ...

Please find a total of 4 websites that are related to

Please find a total of 4 websites that are related to modeling policy with simulations. These can be and include eGovPoliNet and others that have been mentioned in the papers, readings or videos. They can be community ba ...

Keep answers separateapa format1 discuss the role of the

Keep Answers Separate APA format 1. Discuss the role of the configuration control board (CCB) in the process of configuration control using the text Internet and/or your job as reference for full credit Submission Instru ...

Topic we all had the unfortunate experience of seeing how

Topic: We all had the unfortunate experience of seeing how computers can, at times, make life's journey abit more difficult. This is especially true in knowledge centric workplaces. Describe an example of a very poorly i ...

Question - are ltc beds the only place to put us are there

Question - Are LTC beds the only place to put us? Are there other alternatives that are more cost-efficient? Given issues of quality -- either perceived or actual -- in many LTCs, do we really even want to keep tradition ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As