Some of the customers have complained that service is slow. The restaurant is open from 11:00 a.m. to midnight every day of the week. Tony divided the workday into five shifts. The table below shows the minimum number of workers needed during the five shifts of time into which the workday is divided.

Shift

Time

# of Staff Required

1

10:00 a.m. - 1:00 p.m.

3

2

1:00 p.m. - 4:00 p.m.

4

3

4:00 p.m. - 7:00 p.m.

6

4

7:00 p.m. - 10:00 p.m.

7

5

10:00 p.m. - 1:00 a.m.

4


The owners must find the right number of staff to report at each start time to ensure that there is sufficient coverage. The organization is trying to keep costs low and balance the number of staff with the size of the restaurant, so the total number of workers is constrained to 15.
Based on these factors, recommend the staff for each shift to accommodate the minimum requirements for customer service.

Attachment:- BenchmarkDataAnalysisCaseStudyLinearProgrammingTemplate-1.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92055440

Have any Question?


Related Questions in Project Management

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Check all of the following that arenbsptrue for top-down

Check all of the following that are  true for top-down estimates (when being compared with bottom-up estimates). Make sure your answer reflects what is correct for  Top-Down Estimates .  Lower cost to create estimate Hig ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

Project proposal -project - plan for implementing spc for

PROJECT PROPOSAL - Project - Plan for implementing SPC for improvement Introduction/aims/objectives - 200 words max Indicative literature review - 500 words max Indicative research methodology - 500 words max An idea to ...

Annotated bibliographythis table lists criteria and

Annotated Bibliography This table lists criteria and criteria group name in the first column. The first row lists level names and includes scores if the rubric uses a numeric scoring method. Criteria Exemplary Competent ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

You are recently assigned to manage an effort to upgrade

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your compan ...

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

Assignment 1 the core values and principlesplease have the

Assignment 1: The Core Values and Principles Please have the following titles and include content as per assignment instructions under each paragraph: History of Agile project management. Philosophy and purpose of Agile ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As