1) The schedule change control system includes:

A) Requirements for reporting schedule performance
B) Requirements for measuring schedule performance
C) Methods for assessing magnitude of schedule variations
D) Approval levels essential for authorizing schedule changes

2) An activity has the early start date of 10th and a late start date of the 19th. The activity also has duration of 4 days. There are no nonworkdays. From the information given, what could be concluded about activity?

A) Total float for the activity is 9 days.
B) The early finish date of activity is the end of the day on the 14th.
C) The late finish date is the 25th.
D) The activity could be completed in 2 days if the resources devoted to it are doubled.

3) Several types of float are found in project networks. Float that is used by particular activity and does not affect float in later activities is called:

A) Extra float
B) Free float
C) Total float
D) Expected float

4) The main difference between PERT and CPM is that PERT:

A) Uses distribution’s mean (expected value) in computing schedule
B) Uses the most likely estimate to compute float
C) Focuses on computing float to find out which activities have the least scheduling flexibility
D) Includes non-sequential activities like loops or conditional branches as part of the diagram

5) In project time management, crashing means:

A) Reducing project duration by redefining logical relationships
B) Reducing computer network downtime for schedule risk modeling
C) Applying additional resources to all project activities
D) Applying additional resources to critical path activities by priority

6) During activity definition, a team member identifies the activity which needs to be accomplished. Though, another team member believes that activity is not part of project as interpreted by project charter. What must the project manager do?

A) Try to build the consensus of the team.
B) Make the decision about inclusion herself
C) Talk with the end-user
D) Talk with the project sponsor

7) You are five-and-a-half months of work, project is on schedule and budget, but the project sponsors are not satisfied with the deliverables. This situation would delay the project completion by one month. The MOST important process that can have prevented this situation is:

A) Risk monitoring and control
B) Schedule control
C) Scope planning
D) Scope change management

8) You are a project manager on a US $5,000,000 software development project. While working with your project team to develop the network diagram, your data architects suggest that quality can be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with the article from leading software development journal. This type of input is called a(n):

A) Mandatory dependency
B) Discretionary dependency
C) External dependency
D) Heuristic

9) A project manager is asking team members about time estimates for their tasks and developing agreement on the calendar date for each task. In which of the following actions is the project manager involved?

A) Activity sequencing
B) Schedule development
C) Scope definition
D) Initiation

10) During execution, a main problem occurred that was not included in risk response plan. What must you do FIRST?

A) Create a workaround
B) Revaluate the risk identification process
C) Look for any unexpected effects of the problem
D) Tell management

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M94610

Have any Question?


Related Questions in Project Management

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

Define a strategic information system give two examples of

Define a strategic information system. Give two examples of these systems

How does developing interpersonal skills enhance individual

How does developing interpersonal skills enhance individual and team performance

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Leading lean projects assessment case study - continuous

Leading Lean Projects Assessment Case study - Continuous Improvement Introduction - Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the t ...

Your essay should be a properly constructed academic essay

Your essay should be a properly constructed academic essay of 5,000 words. It should contain an effective introduction, body and conclusion. The introduction should introduce the essay and include your argument. The body ...

Advanced topics in project management assignment -outline -

Advanced Topics in Project Management Assignment - Outline - Project management is a highly regarded discipline in engineering. It experienced a number of changes or "natural evolution" in the last century, influenced by ...

Define the kano model and how it helps in gathering

Define the Kano model and how it helps in gathering customer requirements.

You are recently assigned to manage an effort to upgrade

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your compan ...

How might researchers study the effectiveness of inclusive

How might researchers study the effectiveness of inclusive leadership with regard to overall organizational effectiveness and competitiveness?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As