A construction project was 40% complete at month five. Actual cost so far was $100,000; schedule variance was $20,000 and spending variance was $-15,000. find out the earned value completed and total planned cost for project at completion.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M933238

Have any Question? 


Related Questions in Project Management

Discussionproject scheduleto develop a schedule for a

DISCUSSION Project Schedule To develop a schedule for a project, we will use the concept of a project network, which shows work activities taken from the work breakdown structure and is organized according to the logical ...

Closing the great health care divide with pattern

CLOSING THE GREAT HEALTH CARE DIVIDE WITH PATTERN RECOGNITION AND DATA - MINING TECHNOLOGIES In today's world, people, cultures, and nations are distinguished by which side of the " great divides" they are on. There are ...

A local health club is running a promotional campaign that

A local health club is running a promotional campaign that promises you can lose an inch a month off your waist if you join the club and follow its program. How might this claim cause a communications gap? What should th ...

International truck makes a huge bet on a service -

INTERNATIONAL TRUCK MAKES A HUGE BET ON A SERVICE - ORIENTED ARCHITECTURE Service-oriented architectures (SoAs) do seem to be the future for integrated IT systems within an organization, bringing together both applicatio ...

1 there are two general approaches to the system

1. There are two general approaches to the system development life cycle. One is called a predictive approach and the other is the adaptive approach. Compare and contrast these two approaches. 2. In system development we ...

He has heard of eoq as a basis for setting the length of

He has heard of EOQ as a basis for setting the length of production runs. What values should he assign to cp and cH for his operations?

Taskvarious tasks as outlined below after the case

Task Various tasks as outlined below after the case background. Case Background As the project manager you are required to present an initial project report to the project sponsor that shows how you propose to implement ...

What are the assumptions of the basic eoq model and to what

What are the assumptions of the basic EOQ model, and to what extent do they limit the usefulness of the model?

Project management and erppart 1 answer the module review

Project Management and ERP Part 1: Answer the module review questions listed below. 1. What is the role of a project manager and program manager? What are the skills, knowledge, and abilities required to be a project man ...

Discussionagile schedule development gradedas we have seen

DISCUSSION Agile Schedule Development (graded) As we have seen, traditional and Agile schedule developments are quite different. Agile project management was originally developed to do software development. Could a tradi ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro