Question:

Prepare a memo that addresses the following questions:

1. Which if any of the resources are overallocated?

2. Assume that the project is time constrained and try to resolve any overallocalion problems by leveling within slack. What happens?

3. What is the impact of leveling within slack on the sensitivity of the network?

Include a Gantt chart with the schedule table after leveling within slack.

4. Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens? What are the managerial implications?

5. What options are available at this point in time?

Include a Gantt chart with the schedule table after leveling outside of slack.

Note: No splitting of activities is allowed.

Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.

Part B

When you show the resource-constrained network to top management, they are visibly shaken. After some explanation and negotiation they make the following compromise with you:

- The project must be completed no later than February 2, 2012 (530 days).
- You may assign two additional development teams.
- If this does not suffice, you may hire other development teams from the out-side. Hire as few external teams as possible because they cost $50 more per hour than your inside development people.

Internal Development

Add as many development units (teams) as needed to stay within the 530 days. If you need more than two internal development units, then hire as few external teams as necessary. Select the cheapest possibility! Change as few activities as possible. It is recommended you keep work packages which require cooperation of several organizational units inside your company. You decide how best to do this.

Hint: Undo leveling prior to adding new resources.

Once you have obtained a schedule that meets the time and resource constraints, prepare a memo that addresses the following questions:

1. What changes did you make and why?

2. How long will the project take?

3. How did these changes affect the sensitivity of the network?

Include a Gantt chart with a schedule table presenting the new schedule.

Part 4

Based on the file created at the end of Part 3, prepare a memo that addresses the following questions:

1. How much will the project cost?

- After creating the resource pool, copy the screen image of Resource Sheet and paste into the Word document.

- After assigning resources, copy the screen image of the data entry screen and paste into the Word document.

- After time-constrained scheduling, copy the screen image of Resource Sheet and paste into the Word document. The Resource Sheet should show the resources that over-allocated.

- After resource-constrained scheduling, copy the screen image of Resource Sheet and paste into the Word document. The Resource Sheet should show the resources that over-allocated.

Part 3B

- After adding the two internal development teams and doing time-constrained resource scheduling, copy the screen image of Resource Sheet and paste into the Word document. The Resource Sheet should show the resources that over-allocated.

- After adding the two external development teams and doing time-constrained resource scheduling, copy the screen image of Resource Sheet and paste into the Word document. The Resource Sheet should show the resources are no longer over-allocated.

- After generating the Cashflow report, copy the screen image and paste in to the Word document. Change time scale to months.

- Answer all the questions given in Part 3 (five questions from Part 3A and three questions from Part 3B) and Part 4 (all questions). Submit your answers along with the screen shots as listed above as Appendices to the instructor through the Assignment tab on the Blackboard for evaluation.

In addition to the general instructions included in the Overview of this topic, you might find the following notes helpful in doing the Conveyor Belt homework.

Part 3A Notes

- Enter resource names from Table A2.12. For "Assembly/Test" enter "Assembly" for consistency with Table A2.11.
- Enter one team as 100% and two teams as 200% under Maximum Units.

Part 3B Notes

1. Add the two internal development teams for a total of four internal development teams to the resource pool. Level within the available slack (to complete the project within 530 days). If no resources are over-allocated, you have achieved your objective of completing the project in 530 days at the minimum cost. If any resources are still over-allocated, go to the next step.

2. Add the two external development teams as "DevelopmentX" to the resource pool. The external development teams are added as "DevelopmentX" since they are paid at a higher standard rate ($100 per hour). Identify the resources and the activities that are over-allocated through the Resource Usage view by scrolling horizontally. Make a note of the activities.

3. Select the shortest activity from the over-allocated activities from the previous step and change the resource assigned from Development to "DevelopmentX". Level within the available slack (to complete the project within 530 days). If no resources are over-allocated, you have achieved your objective of completing the project in 530 days at the minimum cost. Otherwise, identify the resources and the activities that are over-allocated through the Resource Usage view by scrolling horizontally. Make a note of the activities.

4. Repeat step the previous step until no resources are over-allocated, and you have achieved your objective of completing the project within 530 days at the minimum cost.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91870840
  • Price:- $50

Priced at Now at $50, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As