Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Project Management Expert

Question:

Case Discussion: CyClon Project

This is a case on new product development in Chapter 6. Developing new products is a very important set of projects, where project management is very usefully applied.

This case is also a mini-exercise in Microsoft Project. It shows how concurrent engineering can be implemented through start to start lags in new product development projects.

It brings out some very important points about using the lags and their impact on the project network and the completion of the project.

Use Microsoft Project to do the network planning for the case and then answer the questions given in part A, part B, and part C of the case.

Part A. Create a network based on the above information. How long will the project take? What is the critical path?

Project Duration: 80 days

Critical Path:

2, 3, 5, 6, 7, 8, 10, 11, 12, 13

Design, Procure prototype parts, assemble prototype, laboratory test, field test, adjust design, order custom components, assemble test production unit, test unit, document results

Part B

Reconfigure the CyClon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule? On the amount of work required to complete the project?

Duration(after lag): 101 days

The impact on the original schedule is that these adjustments added 21 days to the duration. The work required is still the same, but there are waiting periods now for parts to be delivered for the 3 tasks that were adjusted.

Part C

Reconfigure the CyClon schedule by entering all nine start-to-start lags. What impact did these lags have on the original schedule (Part A)?

The nine start-to-start lags shortened the duration of the project in comparison to part A. The new duration of the project is 65 days. There was also a change in the critical path. Now Procure prototype parts(#3) is not a critical task and Fabricate Parts(#4) is a critical task. The sensitivity of the network hasn't changed much, but where Fabricate Parts(#4) had 2 days of slack, now Procure prototype parts(#3) has only 1 day of slack. Everything else remains the same. Management would like this solution because it cuts about one fourth of the project duration off and the project will be completed in less time and free up the resources needed that could be used for other projects.

How long will the project take? Is there a change in the critical path? Is there a change in the sensitivity of the network? Why would management like this solution?

Attachment:- case - cyclon project.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91829665
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Project Management

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

What is the current state or condition of information

What is the current state or condition of Information Technology Project Management? What are the challenges and complexities faces by many IT Project Managers of today?

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

Assessment descriptionyou are required to read a case

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. The case study will ...

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

42908 assessment task - project proposal1 executive summary

42908 Assessment Task - Project Proposal 1. Executive Summary - Brief overview of project, main aim of project, potential findings and conclusions. 2. Introduction - Presents general project area, relevance of project, s ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Discuss the different approaches to developing either a

Discuss the different approaches to developing either a Product Breakdown Structure (PBS) OR a Work Breakdown Structure (WBS).

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

What is fast tracking and its impact on the project as it

What is fast tracking and its impact on the project as it relates to project management

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As