Ask Project Management Expert

Question

1. In a strong matrix structure, employees take daily direction from:

  1. Project manager only
  2. Both, but the project manager has greater influence
  3. Both, but the functional manager has greater influence
  4. Functional manager only

2. If the schedule variance is positive and the cost variance is negative, the project's status is:

  1. Over budget and behind schedule
  2. Under budget and ahead of schedule
  3. Over budget and ahead of schedule
  4. Under budget and behind schedule

3. Which category of projects would involve a large number of functional units where the workers may be assigned either part-time or full-time?

  1. Special
  2. Individual
  3. Staff
  4. Matrixed

4. Which type of chart provides the least "predictive" value?

  1. PDM
  2. ADM
  3. PERT
  4. Bar chart

5. Scope creep is generally the result of:

  1. Too much detail in the specifications
  2. Having too many levels in the WBS
  3. Poorly defined SOW
  4. Having the wrong people assigned to the project

6. Which of the following is the role of the PM rather than the role of the functional manager?

  1. Where it will be done
  2. How the work will be done
  3. Who will do it
  4. What work will be done

7. The balance between quality and cost is called:

  1. Produceability
  2. Salability
  3. Availability
  4. Operability

8. The EVMS term that represents the value of work actually accomplished is:

  1. BAC
  2. AC
  3. EV
  4. PV

9. Which of the following would be the first item to be discussed in the initial kickoff meeting for a project?

  1. Understanding of the budget
  2. Understanding of the schedule
  3. Understanding of the requirements
  4. Understanding of the plan

10. Quality is defined by the:

  1. Project team
  2. customer
  3. Project manager
  4. Project sponsor

11. Which of the following people has the greatest influence on how much authority a project manager will possess on a given project?

  1. The project sponsor
  2. The customer
  3. The project manager's line manager
  4. The project manager himself / herself

12. A project manager desires a work breakdown structure that goes through 6 levels of detail. Level 3 through level 6 would most likely be prepared by:

  1. Customer
  2. Subject matter experts
  3. Project manager
  4. Project sponsor

13. In which project life cycle phase does quality begin?

  1. Initiation / planning
  2. Monitoring & control
  3. Closure
  4. Implementation

14. Project management restructuring allowed companies to manage projects that _____.

  1. Had undefined objectives
  2. Could not be handled by the traditional organization
  3. Did not require effective cost control
  4. Require little functional integration

15. Risk constitutes a lack of knowledge _____.

  1. Of future events
  2. About the estimates
  3. About the customer's requirements
  4. About the environment

16. The two primary components of a risk are:

  1. The probability and the impact
  2. The impact and the event
  3. The impact and the amount at stake
  4. The event and the probability

17. Which of the following standard project estimating techniques is usually accomplished in weeks?

  1. Engineering
  2. Parametric
  3. Analogy
  4. Grassroots

18. The hardest part in creating a best practices library is:

  1. Storage
  2. Classification
  3. Evaluation
  4. Knowledge transfer

19. A typical project office (not to be confused with a project management office) responsible for the management of a large project includes the project manager and the:

  1. Project sponsor and assistant project managers
  2. Assistant project managers
  3. Assistant project managers and functional managers
  4. Project sponsor

20. Industries that have _____ tasks and operate in a _____ environment demonstrated the greatest need for project management.

  1. Complex; Dynamic
  2. Simple; Static
  3. Complex; Static
  4. Simple; Dynamic

21. Pricing out the construction cost of a home by a cost per square foot would be representative of a(n) _____ estimate.

  1. Grassroots
  2. Parametric
  3. Engineering
  4. Analogy

22. The collective term for the formal quality activities and processes is called:

  1. Quality control
  2. Quality visions
  3. Quality assurance
  4. Quality policies

23. The difference between the cost baseline and the contracted cost is the:

  1. Profit
  2. Management reserve
  3. Cost of scope changes
  4. Cost at completion

24. Plans such as the cost plan, schedule plan and quality plan are referred to as:

  1. Subsidiary plans
  2. Specialized plans
  3. Integration plans
  4. Functional plans

25. Companies can become reasonably mature in project management by designing the right support systems. In general, how much time usually elapses after maturity before a company becomes excellent in project management execution?

  1. 2 years
  2. 1 year
  3. 5 years
  4. 10 years

26. The best source of revenue for a customer-requested scope change is:

  1. A customer-funded contract amendment
  2. Profits
  3. Management reserve
  4. Undistributed budget

27. During the 1970s and 1980s, formal project management practices were put in place because the constraints were _____ and _____ boundaries had to be crossed

  1. Tight; few
  2. Tight; several
  3. Loose; few
  4. Loose; several

28. A charting technique designed to illustrate the inductive and deductive reasoning necessary to achieve some objective is called a _____ Diagram / network

  1. Descriptive
  2. Intuition
  3. Gantt
  4. Logic

29. Which of the following is often overlooked when planning and budgeting a project?

  1. Customer's milestones
  2. Timing of the deliverables
  3. Number of meetings with the customer
  4. Cost and size of contractual documentation

30. What is the project sponsor's responsibility with regard to the WBS preparation?

  1. The sponsor should not be involved in WBS development.
  2. Make sure all work packages are well-defined.
  3. Make sure that the management levels of the WBS are correct.
  4. Make sure that the technical levels of the WBS are correct.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91392888
  • Price:- $30

Guranteed 24 Hours Delivery, In Price:- $30

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As