Question: Using the activity table below, construct a CPM/PERT network noting the activity numbers and durations. Identify the critical path through the network, determine the project completion time, and determine the earliest and latest end dates for each node. Create your network in Microsoft Word and submit it to your instructor. Please do not draw.

Activity

Predecessor

Time (months)

1

-

10

2

-

1

3

-

6

4

2

3

5

1,3,4

5

6

3

8

7

5,6

2

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92727188

Have any Question?


Related Questions in Project Management

Assessment descriptionyou are required to read a case

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. The case study will ...

What are the advantages and disadvantages of cost of poor

What are the advantages and disadvantages of Cost of Poor Quality (COPQ)?

In software development and design how are requirement

In software development and design how are requirement documents used and maintained, especially as requirements evolve? Also, what processes, methods, and techniques are available for maintenance, and how effective are ...

42908 assessment task - project proposal1 executive summary

42908 Assessment Task - Project Proposal 1. Executive Summary - Brief overview of project, main aim of project, potential findings and conclusions. 2. Introduction - Presents general project area, relevance of project, s ...

Project investment analysis assignment -the aim of this

PROJECT INVESTMENT ANALYSIS ASSIGNMENT - The aim of this project is to introduce participants to concepts of Financial Feasibility Modelling and the use of spreadsheets for feasibility exercises. Assume that you have bee ...

Mikes tees a relatively large company that prints t-shirts

Mike's Tees, a relatively large company that prints T-shirts, is developing a system that allows customers to upload their image files on a server and have them printed on T-shirts. The project was drafted and planned to ...

Developing an innovative solution to a problem involves

Developing an innovative solution to a problem involves several steps.kindly elaborate?

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As