Question: Sager Products has been in the business of manufacturing and marketing toys for toddlers for the past two decades. Jim Sager, president of the firm, is considering the development of a new manufacturing line to allow it to produce high-quality plastic toys at reasonable prices. The development process is long and complex. Jim estimates that there are five phases involved and multiple activities for each phase. Phase 1 of the development process involves the completion of four activities. These activities have no immediate predecessors. Activity A has an optimistic completion time of 2 weeks, a most likely completion time of 3 weeks, and a pessimistic Phase 4 involves five activities. Activity Q requires activity K to be completed before it can be started. All three time estimates for activity Q are 6 weeks. Activity R requires that both activity L and activity M be completed first. The three time estimates for activity R are 1, 2, and 3 weeks. Activity S requires activity N to be completed first. Its time estimates are 6, 6, and 9 weeks. Activity T requires that activity O be completed. The time estimates for activity T are 3, 4, and 5 weeks. The final activity for phase 4 is activity U. The time estimates for this activity are 1, 2, and 3 weeks. Activity P must be completed before activity U can be started. Phase 5 is the final phase of the development project. It consists of only two activities. Activity V requires that activity Q and activity R be completed before it can be started. Time estimates for this activity are 9, 10, and 11 weeks. Activity W is the final activity of the process. It requires three activities to be completed before it can be started: activities S, T, and U. The estimated completion times for activity W are 2, 3, and 7 weeks.

(a) Given this information, determine the expected completion time for the entire process. Also determine which activities are along the critical path.

(b) Jim hopes that the total project will take less than 40 weeks. Is this likely to occur?

(c) Jim has just determined that activities D and I have already been completed and that they do not need to be part of the project. What is the impact of this change on the project completion time and the critical path?

Strategic Management, Management Studies

  • Category:- Strategic Management
  • Reference No.:- M92768204

Have any Question?


Related Questions in Strategic Management

Question choose an organization according to the

Question: Choose an organization according to the following: • Current employer • Most recent or former employer • Place of business that you have patronized or have been familiar with over a long period of time. - Avoid ...

Public health law and policy assessment task - legal case

PUBLIC HEALTH LAW AND POLICY Assessment Task - Legal case study addressing a public health issue Background - For this assessment task you will write a case study, in a report format, addressing the legislative and regul ...

Strategic management assignment - authentic research

Strategic Management Assignment - Authentic Research Portfolio This assignment focuses on your understanding and appreciation of Strategic Management Inputs. You are required to identify a corporation in the Agribusiness ...

Management perspectives assignment -learning outcomes -

Management Perspectives Assignment - Learning Outcomes - Critically analyse the roles, functions that managers perform and discuss the challenges and risks they have to address in today's changing organisations. Discuss ...

Assignment competitor analysis and competitive

Assignment: Competitor Analysis and Competitive Strategy Contry: JAPAN for entry in globel market, Company is: TESLA, and local competitotr: Toyota PRIUS and Globel: CHEVY BOLT. Porter's Generic Strategies Sources of Com ...

Business strategy assignment - business strategy

Business Strategy Assignment - Business Strategy: Telecommunication Sector (UK) Purpose of this assignment - This assignment is designed to develop students' awareness of the different kinds of strategy which could be us ...

Stategic management assignment - strategic analysislearning

STATEGIC MANAGEMENT ASSIGNMENT - Strategic Analysis Learning outcomes - Knowledge: Understanding of the origins and various approaches to strategy. Understanding of the complexity of the relationships between the organis ...

Question - conduct an analysis of the socio-culture

Question - Conduct an analysis of the socio-culture implications for managers in the course of doing business between Australia and china and/or India. Use a case study company that has shown success in its global strate ...

Question strategic planning and financial planningprior to

Question: Strategic Planning and Financial Planning Prior to completing this discussion, read Chapter 13 from your course text. Select a health care organization and answer the following questions as they relate to your ...

Case for analysis leading a virtual teamdiscussion

Case for Analysis: Leading a Virtual Team DISCUSSION QUESTIONS 1. What is Johnson's most pressing problem? Why? 2. What can Johnson do to help her team launch the new product within the six-week timeframe? Be specific? 3 ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As