Question 1:

Your company is doing well and has a profit of about $50,000. You want to make your profit work harder so you have looked at some investment opportunities available. They are

• To insulate the current company offices at a cost of $18,000 which will provide a fuel savings of $1,600 per year over the next 10 years.

• To pay the lump sum of $30,000 to the mortgage of $40,000 that has a loan term of 10 years at 6.5% interest per annum.

• To invest $20,000 into a new business, which has been estimated to return the double amount
in 6 years' time.

• To keep the profit $50,000 in an iSaver account earning a fixed interest of 4.5% per annum for 8 years. After 8 years, there will be no interest for this iSaver account.

Assumptions:
- If only a part of the profit $50,000 is invested in a project, the remaining amount is still kept in the pocket (i.e. no investment).
- The investment/cost occurs at the beginning of a year, and the investment benefits are ob- tained at the end of a year.
- iSaver account calculates the compound interest.

(a) Given the profit you have and assuming a discount rate of 4.8%, perform and document appropri- ate NPV calculations for 10 years for all possible investment options you identified. Graph the re- sults to show the payback analysis of each investment option.

You must use Microsoft Excel or an equivalent spreadsheet program to perform and present your calculations.

Do not use the Excel NPV function and demonstrate you understand the formulas by calculating the NPV. You may confirm the calculated NPV using the Excel NPV function.

Ensure you format the spreadsheets so they use references rather than hard coding data. This al- lows experimenting with the data, e.g., if I change the discount rate the data should react and change accordingly.

Use bolding, colors etc. to ensure the data is easy to interpret.

(b) From your calculations in (a), which investment would you take up and why?

Use a Weighted Scoring Model (see an example on pages 154-155 of the textbook) to discuss the results and explain in detail why you have chosen one option over the others. It is not always just the figures that determine the final decision.

Create a report in Word or PDF format to present the outcomes of (a) and (b).

Use the data, graphs etc. created within the spreadsheet program to present the outcomes.

Question 2:

You are in charge of building a new office for your company. After some discussion with your builder, you identified some of the key tasks, the duration and the costs to complete the building. As you are a project manager you have decided to monitor the building progress using Earned Value Management (EVN). Answer the following questions using the following information

ID

Task Name

Cost ($)

Start Date

Duration

1

Lay foundations

18,000

November 1

2 weeks

2

Build frame

34,000

November

4 weeks

3

Install pipes and electrical

10,000

December

6 weeks

4

Make office water-tight

15,000

February

8 weeks

5

Install internal walls and bathroom

20,000

April

12 weeks

6

Install cabinetries

14,000

July

4 weeks

7

Paint office

8,000

August

2 weeks

8

Install light fixtures and appliances

9,000

August

2 weeks

NOTE: Assume that no task is scheduled to run concurrently, e.g., Task 2 starts after Task 1 com- pletes, Task 3 starts only when Task 2 completes, and so on. Also, assume that each month is made up of exactly four weeks.

(a) What is the planned value of the entire project?

(b) The project manager has managed to keep cost to what was originally budgeted above. At this point, the project has completed Task 4. Up to this point,

i. What is the planned value of the project?

ii. What is the actual cost (AC) of the project? Briefly explain how you derive the actual cost.

iii. What is the rate of performance (RP) for each task? Using the RPs obtained, calculate the Earned Value (EV), Schedule Variance (SV), Cost Performance Index (CPI), and Schedule Performance Index (SPI) of the project.

(c) Unfortunately, two trades resigned after Task 5 was completed and this caused the remaining tasks to exceed its original cost and schedule by 25%, 30%, 40% respectively. At the end of the project,

i. What are the CPI and SPI?

ii. How is the performance with respect to cost and time?

iii. Represent the Planned Value (PV), Earned Value (EV) and Actual Cost (AC) in a chart like the example below.

Attachment:- Template.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91619670
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Project Management

Assessment descriptionyou are required to read a case

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. The case study will ...

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

Your essay should be a properly constructed academic essay

Your essay should be a properly constructed academic essay of 5,000 words. It should contain an effective introduction, body and conclusion. The introduction should introduce the essay and include your argument. The body ...

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

Project investment analysis assignment -the aim of this

PROJECT INVESTMENT ANALYSIS ASSIGNMENT - The aim of this project is to introduce participants to concepts of Financial Feasibility Modelling and the use of spreadsheets for feasibility exercises. Assume that you have bee ...

What are the advantages and disadvantages of cost of poor

What are the advantages and disadvantages of Cost of Poor Quality (COPQ)?

This is the brief for the third and final exercise for this

This is the brief for the third and final exercise for this project. Your group has been appointed as Project Manager by The Proprietary Very Limited Corporation (PVLC) to carry out development and feasibility analyses o ...

Check all of the following that arenbsptrue for top-down

Check all of the following that are  true for top-down estimates (when being compared with bottom-up estimates). Make sure your answer reflects what is correct for  Top-Down Estimates .  Lower cost to create estimate Hig ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Advanced topics in project management assignment -outline -

Advanced Topics in Project Management Assignment - Outline - Project management is a highly regarded discipline in engineering. It experienced a number of changes or "natural evolution" in the last century, influenced by ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As