Question 1:  Your firm designs training materials for computer training classes, and you have just received a request to bid on a contract to produce a complete set of training manuals for an 8-session class. From previous experience, you know that your firm follows an 85% learning rate. For this contract, it appears that the effort will be substantial, running 50 hours for the first session. Your firm bills at the rate of $100/hour and the overhead is expected to run a fixed $600 per session. The customer will pay you a flat fixed rate per session (Per Session Price.) If your profit markup is 20%, what will be the Total Price, the Per Session Price, and at what session will you break even?

Answer the following three questions:

  1. What is the Total Price? This is what you would charge the customer so that you can have your profit markup of 20% over all of your costs. I have included a template you can use that includes the formulas for calculating learning curve values in cells B8:B15.  This is the same formula used in the Media One Consultants example from Mantel pp 125 and 126.  You will need to enter all other data.
  2. What is the Per Session Price? This is the revenue that the customer pays you each time you complete a session. It is calculated by dividing the Total Price by the number of sessions.
  3. What is the Break Even Point? At the beginning, your cost per session is more than your revenue per session. Gradually, your cumulative revenue matches the cumulative cost, and eventually exceeds it so that you can end up with the desired profit. The break-even point is the session at which, for the first time, your revenue exceeds your cost.

Question 2: You have just been assigned as Project Manager (PM) to the Kuraiz-Reconda Fiber Optic Cable (KRFOC) project.  You are preparing your cost estimate for the project and your Project Engineer (PE) tells you it will take 300 hours to complete the design effort.  Your Finance Manager (FM) tells you that engineering labor is $100 an hour.  Fortunately for you, unfortunately for them, you are a graduate of UMUC, specializing in project management in general and advanced project management techniques in particular.

Answer the following three questions:

  1. Upon questioning, your PE admits that the 300 hours is just a guess, that under the best circumstances, meaning you quit bugging him with inane questions, it may take only 270 hours. However, it could take as long as 400 hours (if you do not leave him alone to do his job). He stands by his estimate that it will normally take 300 hours.  What is the expected cost for design? 
  2. Thinking back you wonder if all engineers cost $100 per hour.  Upon questioning, your FM admits that this is an average cost, that some are higher, some are lower.  You direct him to give you the distribution of all engineer labor rates.  he replies that the labor rate is normally distributed with a mean of $100 and a standard deviation (he is still not sure what that is) of $3.  Using Crystal Ball (CB), what is the mean cost of your engineering effort?  Be sure to provide the results of your CB simulation.
  3. You are about to present your cost estimate to your sponsor when you remember that he was once a Professor.  You recall, too, that he wore both a belt and suspenders and you suspect that this meant he might be a bit conservative.  You therefore decide to provide an engineering cost estimate such that you are confident that 90% of the time your actual costs would be less than that value and that no more than 10% of the time would you exceed that value.  What is your new estimate of engineering costs?   Be sure to provide the results of your CB simulation.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91224001
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As