Question 1: A project manager has received the following probabilistic estimates for the duration of an activity: optimistic duration is 7 workdays, most likely duration is 8 workdays and pessimistic duration is 15 workdays. What is the PERT weighted average for this activity?

a. 11 workdays

b. 10 workdays

c. 9 workdays

d. 8 workdays

Question 2: Successful project managers employ certain tactics to reduce late stage changes to scope. Which of the following is one such tactic?

a. Route scope change requests through the project sponsor

b. Connect scope change requests to cost and schedule changes

c. Refuse to entertain any scope change requests

d. Assign change requests to future projects

Question 3: As a project manager you understand that you can choose from multiple approaches to generate a work breakdown structure (WBS). Which approach must you check first?

a. Analogy

b. Top-down

c. Guidelines

d. Mind-mapping

Question 4: Project scope management is a set of processes that are used to describe, control and validate the work to be done in a project. What is a purpose of project scope management?

a. To ensure common understanding among stakeholders of the project's products

b. To convince the customers of the importance and quality of the project's products

c. To persuade top management of the necessity of the project's products

d. To protect the project manager from any liability arising from the project's products

Question 5: Project time management involves 7 main processes to ensure that the project is completed on time. Which of the following processes does not work with the project schedule network diagrams?

a. Estimating activity resources

b. Estimating activity durations

c. Defining activities

d. Sequencing activities

Question 6: The government has mandated a new regulation. Your company has made you the project manager responsible to implement the systems to support this regulation. You have been given the discretion to choose a legal team. You contacted three legal teams and are waiting for proposals from them. What dependency of project activities is this?

a. External dependency

b. Legal dependency

c. Discretionary dependency

d. Mandatory dependency

Question 7: Requirements of a project can be collected using many different methods. Which method collects requirements through a comparative study?

a. Observation

b. Survey

c. Benchmarking

d. Interviewing

Question 8: A work breakdown structure (WBS) lists in an organized manner all the tasks of a project. What is the main tool used to create a WBS?

a. Decomposition

b. Template

c. Project management software

d. Brainstorming

Question 9: Which of the following statements about project milestones is not true?

a. Milestones are the most important events

b. Milestones are useful for monitoring progress

c. Milestones are sometimes deliverables

d. Milestones are always without any duration

Question 10: While reviewing the work breakdown structure (WBS) of a project you find that all the tasks are directly related to deliverables. What is missing?

a. Process groups related tasks

b. Project management tasks

c. Customer relationship tasks

d. Team tasks

Question 11: Project managers have many tools and techniques available to support schedule development. Which of the following is the best technique to use when the project manager has a resource limitation?

a. Critical path analysis

b. Gantt chart

c. PERT analysis

d. Critical chain scheduling

Question 12: Incorrect scope definition can lead to expensive rework. Therefore, best practices must be followed to avoid major scope problems. Which one of the following is not a best practice for project scope management?

a. Keep the project large to get benefit of scale

b. Include selected potential users in defining requirements

c. Use proven technology to reduce risks

d. Adhere to project scope management processes

Question 13: You are estimating the duration of an activity in the project. You determine that the activity requires 3 resources working 4 hours a day for 5 days. What is the duration?

a. 60 hours

b. 20 hours

c. 5 days

d. 15 days

Question 14: Which chart is used to evaluate progress on a project by displaying the planned and actual schedules together?

a. Tracking Gantt chart

b. Baseline Gantt chart

c. Evaluation Gantt chart

d. Progress Gantt chart

Question 15: Critical path method is a project network diagramming approach used to predict total project duration. Which of the following is not true of the critical path?

a. Critical path has the least amount of slack

b. Critical path determines the important activities in the project

c. Critical path is the longest path through the network diagram

d. Critical path is the earliest time by which the project can be completed

Question 16: The work breakdown structure (WBS) document should be accompanied by a WBS dictionary. What would you expect to find in this dictionary?

a. Definition of terms of a WBS item

b. Alternative choices for terms in a WBS item

c. Names of people who understand a given WBS item

d. Clarification of a WBS item

Question 17: The scope management plan is an output of the planning scope management process. Which one of the following choices is likely to be in the scope management plan?

a. Type of resources required for the project

b. Process for approving deliverables of the project

c. List of requirements from the project

d. Deadline for completion of the project

Question 18: A project manager takes over a project that is going over schedule and finds that the network diagram is prepared using the arrow diagramming method (ADM). It will be easier to do schedule trade-offs if the network diagram had been prepared using the precedence diagramming method (PDM). What is the main step for converting this network diagram?

a. Use the convert option in the project management software

b. Determine the type of dependencies between the linked tasks

c. Change the arrows to boxes

d. Find an expert

Question 19: Controlling the schedule is the final process in project time management. Which of the following is not a goal of schedule control?

a. Manage schedule changes

b. Know the schedule status

c. Influence the factors that cause schedule changes

d. Establish schedule control thresholds to monitor variances

Question 20: Scope definition process elaborates in detail the work required for the project. Which one of the following is a strong reason for good scope definition?

a. Improves the project work environment

b. Improves the stakeholder commitment to the project

c. Improves the project team performance

d. Improves the accuracy of project budget.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91420637
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As