Question 1 :

A company changes stoping methods and discovers that the new method gives a substantially higher dilution rate and yet the profit margin is higher. Show by simple calculation how this can come about.

Question 2 :

Three basic methods of underground coal mining exist, name the three methods. Briefly compare and contrast the three methods, use sketches where ever possible and discuss the following:

a) Panel/pillar dimensions

b) Production methods

c) equipment

Question 3 :

Discuss the points you would consider when selecting a production method or methods for a particular ore body. Indicate which points you consider to be the most important.

Question 4 :

An ore body is mined by shrinkage stoping from a vertical shaft. Draw one or more simple sections to show the following details:

• Ore/waste pass systems
• Stope development
• Extraction level or levels
• Sub-levels
• Slot raises

Question 5 :

In multiple level room and pillar operations what potential problems exist due to the various levels interacting with each other. What methods are available to limit the effects of this interaction?

Question 6 :

In blockel caving what are the important criteria in planning the layout of development and supervising extraction?

Question 7:

What are the implications in the mining and treatment of sulphide ore, which tends to oxidise readily? What methods could be used to mine such ores?

Question 8 :

Illustrate a modern longwall coalface including the face and a short section of the gates. Note show all equipment and label the diagram clearly.

Question 9 :

Compare and contrast room and pillar mining with longwall mining in terms of economics, safety, productivity and depth of cover.

Question 10 :

Describe a method of open stoping in detail. What are the advantages and disadvantages of open stoping over other methods of mining similar ore bodies?

Question 11 :

To be successful in Sub-level caving, careful controlled draw point mucking must be practiced. Discuss this from a point of view of:

a) An individual draw point

b) A group of closely spaced drawpoints

Question 12 :

Compare and contrast longwall advancing and retreating methods of coal mining.

Question 13 :

A retreat longwall coal mining system utilises twin accesses on both the intake and return sides of a panel whose face width is 300m. If the access drives are 5m wide and chain pillars are 20m wide between the accesses determine the extraction ratio for the following cases:

a) Panel under development

b) Panel under production

It may be assumed that rib pillars 40 m wide are left for support between panels. It can also be assumed that a barrier pillar of 40 m width is left to protect the main mine entries and that the panel length is 3km.

Question 14 :

Describe in detail one method of pillar extraction in room and pillar mining.

Question 15 :

What methods of mining can be applied to the mining of inclined ore bodies dipping in the range 30 to 60 degrees? Describe one such method in detail citing an example of its application.

Question 16 :

Backfill is becoming more widely applicable in underground mining. What methods of backfilling can be applied? Describe these in detail citing
examples of their use, advantages and disadvantages of the method.

Question 17 :

With the aid of sketches describe the mining sequence applied in a mechanised cut and fill mining operation.

Question 18 :

In relation to underground metalliferous mining define:

a) Recovery

b) Dilution

What methods of sampling are available to determine each of the above?

Question 19 :

Describe the Avoca system of Open Stoping

Question 20 :

Describe the components involved in a traditional drill and blast mining cycle and those involved in a continuous mechanised mining cycle. What advantages and disadvantages do both systems of mining have?

Question 21 :

The diagram below illustrates the amount of coal that is left intact after mining in pillars and the amount of coal that is extracted in the rooms. If a1 = 20m, a2 = 22.5 m, b1 = 5m and b2 = 4.5m determine the recovery ratio in a 2.5 m coal seam.

107_What are the important criteria in planning.png

Question 22 :

What do the terms transverse and longitudinal mean with respect to the direction of mining within an orebody?

Question 23 :

Show with the aid of diagrams the development, production and filling phases for a typical open stoping mining setup. What advantages does filling of the stope give?

Question 24 :

Define the following:

a) Stope

b) Overhand mining

c) Underhand mining

d) Extraction ratio

e) Crown pillar

f) Sill pillar

g) Ore pass

h) Waste pass

i) Raise

j) Slot raise

k) Grade

Question 25 :

Define the following terms, diagrams may help:

a) Chain Pillar

b) Barrier Pillar

c) Crown Pillar

d) Sill Pillar

What other types of pillars are commonly used in mining?

Describe a method of pillar design suitable for the design of a room and pillar mining system. What are the main factors that influence the design of such pillars?

Question 26 :

Describe with the aid of sketches the layout of a typical South African longwall gold mining system. What particular advantages does this mining method have for mining at ultra-depths?

Question 27:

Describe a highwall mining technique in detail, if possible giving details of productivity levels that can be achieved.

Question 28:

Describe the longwall top caving mining method

Question 29:

What is square set stoping?.

Question 30:

In a typical block caving operation the following levels exist:

a) Undercut level

b) Draw or production level

c) Ventilation level

d) Transportation level

Describe the operations and requirements for each of these levels, citing examples wherever possible. What factors influence the spacing between these levels?

Question 31 :

Air blasting is not uncommon in block cave mines. Describe how a typical air blast can develop. How can air blasts be minimised and what engineering controls can be applied to ensure this?

Question 32 :

To ensure continuous production from a room and pillar type operation, determine the minimum number of headings required to be operating if the production is to be undertaken using:

a) Traditional drill and blast production methods

b) Continuous miners

What methods of ore transportation are applicable with the above?

Question 33 :

Define the terms over break and under break. What methods can be used to determine these in a typical production stope and what steps can be used to minimise both?

 

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91247818
  • Price:- $125

Priced at Now at $125, Verified Solution

Have any Question?


Related Questions in Project Management

Project proposal -project - plan for implementing spc for

PROJECT PROPOSAL - Project - Plan for implementing SPC for improvement Introduction/aims/objectives - 200 words max Indicative literature review - 500 words max Indicative research methodology - 500 words max An idea to ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

This is the brief for the third and final exercise for this

This is the brief for the third and final exercise for this project. Your group has been appointed as Project Manager by The Proprietary Very Limited Corporation (PVLC) to carry out development and feasibility analyses o ...

The hospitality industry comprises diverse and varied

The hospitality industry comprises diverse and varied functions and scale of operations. Some organisations may be single function business enterprise such as catering organisation. Others may be larger with multiple bus ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Read the article - project management time amp cost

Read the article - Project Management Time & Cost Estimation Techniques: An Overview by Sid Kemp Using this article and other resources that you locate, write a one page paper answering the following points: - Explain wh ...

What is fast tracking and its impact on the project as it

What is fast tracking and its impact on the project as it relates to project management

In software development and design how are requirement

In software development and design how are requirement documents used and maintained, especially as requirements evolve? Also, what processes, methods, and techniques are available for maintenance, and how effective are ...

As a project manager answer these questions1 a how does the

As a project manager answer these questions, 1) a. How does the weighted scoring approach avoid the drawbacks of the NPV approach? b. Can the two approaches be combined? if so How? How are you going to apply this piece o ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year