Project Topic 1: Moore Housing Contractors 

Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in late winter or early spring when the weather begins to moderate and build through the summer and fall. The summer months are a busy time for the realty company, and it believes it can sell the houses almost as soon as they are ready or sometimes before. The houses all have similar floor plans and are of approximately equal size; only the exteriors are noticeably different. The completion time is so critical for Countryside Realtors that it is insisting a project management network accompany the contractor's bid for the job with an estimate of the completion time for a house. The realtor also needs to be able to plan its offerings and marketing for the summer. The realtor wants each house to be completed within 45 days after it is started. If a house is not completed within this frame, the realtor wants to be able to charge the contractor a penalty. Mary and Sandy Moore, the president and vice president of Moore Housing Contractors, are concerned about the prospect of a penalty. They want to be confident they can meet the deadline for a house before entering into any agreement with a penalty involved. If there is a reasonable likelihood they cannot finish a house within the 45 days, they want to increase their bid to cover potential penalty charges. The Moores are experienced home builders, so it was not difficult for them to list the activities involved in building a house or to estimate activity times. However, they made their estimates conservatively and tended to increase their pessimistic estimates to compensate for the possibility of bad weather and variations in their workforce. Following is a list of the activities for building a house and the activity estimates: 


Activity Description Predecessors Time (days) 
a m b 
A Excavation, pour footers - 3 4 6 
B Lay foundation A 2 3 5 
C Frame and roof B 2 4 5 
D Lay drain tiles B 1 2 4 
E Sewer (floor) drains B 1 2 3 
F Install insulation C 2 4 5 
G Pour basement floor E 2 3 6 
H Rough plumbing, pipes E 2 4 7 
I Install windows F 1 3 4 
J Rough electrical wiring F 1 2 4 
K Install furnace, air conditioner C, G 3 5 8 
L Exterior brickwork I 4 6 10 
M Install plasterboard, mud, plaster J, H, K 6 8 12 
N Roof shingles, flashing L 2 3 6 
O Attach gutter, downspouts N 1 2 5 
P Grading D, O 2 3 7 
Q Lay subflooring M, N 3 4 6 
R Lay driveway, walks, landscape P 4 6 10 
S Finish carpentry Q 3 6 12 
T Kitchen cabinetry, sink, and appliances Q 2 4 8 
U Bathroom cabinetry, fixtures Q 2 3 6 
V Painting (interior and exterior) S, T, U 4 6 10 
W Finish wood floors, lay carpet S, V 2 5 8 
X Final electrical, light fixtures V 1 3 4 
1. Develop a CPM/PERT network (draw the network, find expected completion time, variances, ESTs, LSTs, EFTs, LFTs, and slack for each activity, and expected project completion time and critical path). 
2. Determine the probability that the contractors can complete a house within 45 days. 
3. Does it appear that the Moores might need to increase their bid to compensate for potential penalties? 
4. Indicate which project activities Moore Contractors should be particularly diligent to keep on schedule by making sure workers and materials are always available. 
5. Indicate which activities the company might shift workers from as the need arises. 

The Moores also developed the budget for building a house. The budget estimates before project start is provided in the table below: 

Activity Total budgeted cost ($) 
A $20,000 
B $21,000 
C $25,000 
D $5,000 
E $6,000 
F $4,000 
G $15,000 
H $11,000 
I $8,000 
J $7,000 
K $6,000 
L $13,000 
M $6,000 
N $3,000 
O $2,500 
P $3,500 
Q $8,000 
R $11,000 
S $9,000 
T $8,000 
U $4,000 
V $6,000 
W $8,000 
X $2,000

6. Develop budgeted cost estimates per day from the start of the project until its completion using both ESTs and LSTs of each activity. 

In the 12th day of the project, the Moores wanted to know the status of the project. Activities A, B, C, D, and E have been finished and incurred costs of $19,000, $24,000, $25,000, $4,000, and $8,000, respectively. Activity G is 80% finished with incurred costs of $13,000, activity H is 60% finished with incurred costs of $7,000, and activity F was just started (5% completed) and incurred a starting cost of $600. The other activities have not been started. 
7. Is the project of building the first house on schedule? 
8. What is the value of work completed? 
9. Are there any cost overruns? 

Suppose the Countryside Realtors wanted to have each house finished in 35 days. Moore Contractors has a plan developed for this type of situation, as well. This plan includes adding extra resources such as equipment and people to each of the activities A - X needed for building a house. The crash time and crash cost for each activity are presented in the table below: 

Activity Crash time Crash cost 
A 3 $28,000 
B 2 $26,000 
C 3 $31,000 
D 1 $6,500 
E 1 $7,000 
F 3 $5,000 
G 2 $18,000 
H 3 $12,000 
I 2 $10,000 
J 1 $7,500 
K 3 $9,000 
L 3 $19,000 
M 6 $8,000 
N 1 $4,000 
O 1 $3,000 
P 2 $4,000 
Q 3 $10,000 
R 4 $13,000 
S 3 $12,000 
T 3 $9,000 
U 2 $6,000 
V 5 $9,000 
W 4 $9,000 
X 1 $4,000

10. Calculate the project crash cost under this scenario. 
11. Using the crash time and crash cost in the table above, calculate the shortest possible delivery time and its cost.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91253321

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As