Universal Systems of Florida (USF) produces subcomponents for several large corporations. USF growth has been based on maintaining high quality on time deliveries of cutting edge technologies. The senior management has been reviewing your proposed project with several large corporations and agreement was reached that if you can deliver your product on schedule they will include this upgrade as part of a new system. After a meeting late Thursday night you received an email from your boss that stated, Congratulations your project is approved. He also stated that Schedule is a priority, and don't be late. This is your first project where you have the lead. Your team received word on Friday morning that the project was approved. Your team provided the updated network below, which is a standard procedure to keep everyone informed.

For the network above answer the following questions;

a. The project is estimated to take how many days?

b. How many critical paths are there?

c. Project started on time yesterday. After only one day into project you receive a call informing you that due to a fire the "Design of Cust. Parts" is delayed 5 days. What potential impact will this have on your project?

d. What immediate actions will you take?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M9356829

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Assessment descriptionyou are required to read a case study

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. Case Study - DeGrand ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

How might researchers study the effectiveness of inclusive

How might researchers study the effectiveness of inclusive leadership with regard to overall organizational effectiveness and competitiveness?

Developing an innovative solution to a problem involves

Developing an innovative solution to a problem involves several steps.kindly elaborate?

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

Discuss the different approaches to developing either a

Discuss the different approaches to developing either a Product Breakdown Structure (PBS) OR a Work Breakdown Structure (WBS).

What is the current state or condition of information

What is the current state or condition of Information Technology Project Management? What are the challenges and complexities faces by many IT Project Managers of today?

What are the advantages and disadvantages of cost of poor

What are the advantages and disadvantages of Cost of Poor Quality (COPQ)?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As