Project Scheduling

Professor Al E. Gator, who has been teaching Management Science at the Swamproot University School of Business, has decided to publish his own textbook based on the materials that he has developed over the past 25 years. He expects his textbook to be a big hit, as does his publisher, John Smiley, & Sons, Inc.

Professor Gator asked his graduate assistant, Amanda, to help him organize the schedule of core macro-level activities that constitute this project. She has estimated that it will take about 21 months (i.e., 452 business days) to complete the entire publishing process. After discussions with Smiley and Sons, Amanda determined that Al will lose about $10,000 per business day in book royalties from textbook sales if the project is not completed by the deadline.

Table 1 shows the precedence relationships among the macro-level activities that constitute the upcoming project, as well as the optimistic(a), most likely(m), and pessimistic(b) activity times estimated in business days.

Table 1

MACRO-

ACTIVITY DESCRIPTION

IMMEDIATE

ESTIMATED ACTIVITY TIMES

LEVEL

 

PREDECESSOR

(IN BUSINESS DAYS)

ACTIVITY

 

 

Optimistic

Most Likely

Pessimistic

A

Al arranges for a meeting with

-

8

10

12

 

Smiley editor to discuss the project

 

 

 

 

B

Al prepares an outline for the text

A

20

22

25

C

Al prepares and sends editor two

A

51

55

59

 

sample chapters

 

 

 

 

D

Al prepares and sends a formal

B,C

4

5

5

 

proposal to Smiley

 

 

 

 

E

Editor engages faculty for review

C

10

10

12

 

and compiles their suggested

 

 

 

 

 

changes

 

 

 

 

F

Al implements editor's changes on

D, E

8

10

13

 

the two sample chapters

 

 

 

 

G

Al negotiates final contract details

E

18

19

24

 

with Smiley

 

 

 

 

H

Al prepares and sends the

E

172

185

197

 

remaining seven chapters to editor

 

 

 

 

I

Al drafts all figures and graphs

F, H

51

56

65

J

Editor reviews the preliminary

I

9

10

13

 

figures and graphs

 

 

 

 

K

Editor reviews the entire text and

J

53

55

61

 

makes final changes

 

 

 

 

L

Al reviews editor's final changes

K

8

9

11

M

Smiley marketing department

G

43

50

58

 

executes promotional program for

 

 

 

 

 

text

 

 

 

 

N

Smiley prints copies of the text

L

32

37

41

O

Smiley distributes copies to

M, N

11

12

14

 

warehouses

 

 

 

 

P

Smiley distributes copies from

O

7

7

7

 

warehouses to campus bookstores

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Part A.

Please use your understanding of project scheduling to help Amanda address the following:

1. Please identify the critical path using the activity letters provided, and explain the significance of the critical path.

2. With respect to the total project, what is your best estimate of:

a. the expected project-completion time?

b. the most-likely project-completion time?

c. the variance of the project completion time?

Also, one-by-one, please discuss briefly the specific statistical assumptions, if any, that you made in answering questions 2a., 2b., and 2c.

3. Please create the fully-labeled network diagram for the project using the activity letters provided as labels, and explain its usefulness in managing this project. What information and insights does the labeled network diagram provide?

4. Please create the Gantt chart and explain its potential incremental usefulness in managing this project. What additional information and insights does it provide above and beyond those provided by the network diagram in question 3?

5. Please calculate the free slack for activities F and M. What do they tell you about the risk of the critical path identified in question 1 being overtaken by another path when the project is actually conducted?

6. On which activity would you focus on most heavily to reduce the total-project-completion time? Please explain how you arrived at your answer.

7. How likely it is that the project will not meet the current deadline of 452 business days? Please explain how you arrived at your answer.

Part B.

Suppose that Professor Gator, who is extremely risk-adverse, feels that the probability of missing the 452-business-day deadline (from Q.A.7) is too high. As a consequence, he wants to have Amanda evaluate various activity-crashing scenarios that would reduce the likelihood of incurring a penalty cost for missing this completion time. Since the most-likely activity-time estimates (m's) provided in Part A are frequently closer to their respective optimistic time estimates (a's) than they are to their pessimistic estimates (b's), Al wants to use a more conservative approach to estimating each activity's normal time. He has decided to use the mid-point between a and b in estimating each activity's normal time [i.e., NT=(a+b)/2] instead of using m or m. He feels that optimistic time estimates from Part A are good estimates for the crash times. The corresponding normal and crash direct costs for all 16 activities are presented in Table 2.

Table 2

Activity

Normal Cost

Crash Cost

A

$0

$0

B

$16,500

$24,300

C

$20,500

$48,700

D

$5,000

$8,500

E

$42,300

$73,700

F

$23,300

$40,500

G

$20,500

$30,500

H

$57,500

$81,500

I

$17,300

$25,500

J

$4,500

$5,700

K

$11,900

$14,500

L

$3,000

$6,500

M

$227,100

$285,500

N

$118,300

$149,300

O

$47,500

$93,300

P

$42,900

$42,900

Please use your understanding of project scheduling to help Amanda address the following:

1. What is the normal project duration (i.e., without any crashing)? What is the associated total direct cost? What is the associated likelihood that the target completion time of 452 business days will be met? Please explain the rationale that you used in arriving at your probability estimate.

2. What is the minimum project duration? What is the associated all-crash total direct cost? What is the critical path associated with the all-crash scenario?

3. Which activities have been crashed without reducing the total project completion time? After accounting for activities that do not need to be crashed, what is the minimum total direct cost associated with the minimum project duration? What are the savings in total direct cost due to optimization of the crashing process? Does the critical path differ from your answer to B.2? Explain why or why not.

4. Provide the Crash Cost per Day for each activity. From a cost perspective, which activity should be crashed first? Which activity, or activities, should Amanda recommend crashing in order to reduce the project completion time by 10 business days for the minimum cost? What is the crash cost for those 10 days?

5. Professor Gator agrees with Amanda's recommendation to crash by 10 business days, but wants to go even further and crash by a total of 20 business days. What is the difference in cost between crashing 20 days and 10 days? How can you explain this difference?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91418229
  • Price:- $60

Priced at Now at $60, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As