Ask Project Management Expert

Project Planning and Control

Changes to Assignment for Part C

Please make the following changes to your Project Planning assignment Gantt Chart:

1. At the time of preparing the proposal for your project, your supplier for the IVR system had asked you to assume delivery within 4 weeks of order placement. You had accordingly prepared your project schedule. Unfortunately,due to some problems faced by them, your supplier has just informed you that the delivery of the IVR system will be delayed by about 2 weeks. This means the delivery date for the smart devices will no longer be 4 weeks but 6 weeks from the date of order placement.

2. During one of the project review sessions, the Chief Executive of STS was informed that the current scope did not have a provision of notifying the customer the status of the booking. The Chief Executive was not happy and has asked the Operations Manager to include this in scope. Customers should be provided with ready access to information on the status of their bookings and should be notified when they could expect to be picked up. This is an increase to the scope of the project.

3. One of your Business Analyst who was earmarked to gather requirements for the Taxi Booking System has suddenly met with an accident and the doctor treating him has advised that he will not be able to resume work for the next 8 weeks. There is no one available within the organisation to immediately take his place and therefore you are forced to look for an equally competent contract staff as his replacement. The contract staff is expected to cost the project double the rate of your Business Analyst. Also, it will take you a week to find this equally competent Business Analyst from today (18thSep).

For each of the above changes, create an Impact Analysis (see an example on Moodle), and then revise your Gantt chart to incorporate the above changes.Where appropriate, these must also be mentioned in your two-weekly Status Report.

Each of these changes could impact either the time line and/or the budget. The impacts to both time line and budget should be reflected in the Gantt chart.

It is recommended that you do each report and the changes in sequence, so that you can comment on the progressive impact in each case.However, we only need the final Gantt chart delivered in Part-C.

Attachment:- Project planning and control.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92510382
  • Price:- $110

Guranteed 48 Hours Delivery, In Price:- $110

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As