Ask Project Management Expert

Project Planning & Management Group Assignment-

Question 1 - You are a project manager who is tasked to produce a driverless truck. To do this, you first need to build and test a prototype of driverless truck in the lab. Below are activities involved to build the truck. Each activity has the duration and its predecessor activities.

Activity

Description

Duration

Predecessor

1

Design

5

N/A

2

Procure prototype parts

8

1

3

Fabricate parts

6

1

4

Assemble prototype

5

2,3

5

Laboratory test

6

5

6

Field test

8

5

7

Adjust design

5

6

8

Order stock components

5

7

9

Order custom components

10

7

10

Assemble test production unit

10

8, 9

11

Test unit

5

10

12

Document results

3

11

Your next steps are:

a. Build an AoN diagram with forward and backward pass to find the ES, LS, EF, LF and Slack days for each activity listed above. (Note: Assume the first activity starts on day 0)

b. Find the critical path in your AoN diagram and the total duration of the project.

c. Transfer all information from the AoN diagram to MS Project and create a Gantt Chart. (Note: Base your plan on the following guidelines: eight-hour days, seven-day weeks, no holiday breaks, 2nd January is the project start date.).

Question 2 - Read the Advantage Energy Technology data Centre Migration and answer the following sub-questions:

a. Generate a priority matrix for AET's system move and provide a justification for your choices.

b. Develop a WBS table for Brian's project. Include duration (days) and predecessors.

c. Develop an AoN diagram with forward and backward pass to find the ES, LS, EF, LF and Slack days for each activity listed above. (Note: Assume the first activity starts on day 0)

d. Use Microsoft Project or some other project management software available to you to develop a schedule for this project.

Question 3 - You have prepared the following schedule for a project in which the key resource is an injection moulding machine. This schedule is contingent on having 3 such machines.

2039_Figure.png

You receive a call from your partner, Benson, who desperately needs 1 of your injection moulding machines. You tell Benson you would be willing to let him have the machine if you are still able to complete your project in 10 months.

a) Develop a resource schedule and draw a loading chart to see if it is possible to complete the project in 10 months with only 2 machines. Be sure to record the order in which you schedule the activities using scheduling heuristics.

b) Assume that activity 5 requires 2 machines, while all other activities require 1 machine. No splitting of activities is possible. Can you say yes to Benson's request?

Write a paragraph answering the question: "Can you say yes to Benson's request?"

Indicate any assumptions you made and show calculations and justification to clearly indicate how you arrive at your answers.

Question 4 - Assume that you have the following decision-making options:

(1) make the decision on your own with available information,

(2) consult others before making a decision, and

(3) call a meeting and reach a consensus, seeking to arrive at a final decision everyone can agree on.

a) Research and find an example online of two difficult business decisions.

b) Write a paragraph in your own words to describe each decision (1/2 to 1 page total).

c) Write another paragraph for each decision to discuss which approach would you use to make the decision and why.

Remember to indicate where your information came from.

Question 5 -

a) On day 47 a project has an earned value of $650, an actual cost of $690, and a planned cost of $590. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

b) Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 5 and the end of period 9.

c) From the data you have collected and computed for periods 5 and 9, what information are you prepared to tell the customer about the status of the project at the end of period 9?

Use the following information to help you to produce a report for period 5 and period 9.

End of Period 5

Task

Actual % Complete

EV

AC

PV

CV

SV

A

Finished

 

310

420

 

 

B

55%

 

1100

830

 

 

C

39%

 

530

650

 

 

D

0%

 

0

 

 

 

E

0%

 

 

 

 

 

Cumulative Totals

 

 

 

 

 

 

End of Period 9

Task

Actual % Complete

EV

AC

PV

CV

SV

A

Finished

 

310

420

 

 

B

Finished

 

2500

2500

 

 

C

Finished

 

1700

1700

 

 

D

30%

 

400

0

 

 

E

39%

 

400

0

 

 

F

5%

 

0

0

 

 

Cumulative Totals

 

 

 

 

 

Clearly show or explain how you arrived at your answers (simply writing the answer alone is not enough). Make sure that you justify your opinions.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91927173

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As