Q1. Consider the following project activities

Activity

Duration (Days)

Immediate Predecessors

A

4

None

B

3

A

C

7

A

D

9

A

E

8

A

F

7

B

G

6

C

H

13

C

I

4

D, E

J

12

E

K

1

E

L

5

F, G,H

M

4

I, J, K

N

5

L, M

a. Draw the network diagram.

b. Show the early start, early finish, late start, and late finish times.

c. Show the critical path.

d. Suppose you have the option of shorting any or all of C, D, H and J each one day, which would you shorten?

e. What is the new critical path and earliest completion time?

Q2. Oxford RV is planning to launch a new model of RVs. The project activities are as   follows:

ACTIVITY

 

Immediate Predecessors

Required Time (Weeks)

Cost

Normal

Crash

Normal

Crash

A

Hiring workers

None

8

5

$4,000

$10,000

B

Install equipment

None

6

5

$7,000

$11,000

C

Order materials

None

3

2

$20,000

$21,000

D

Test equipment

B

4

2

$5,000

$10,000

E

Train workers

A,B

6

4

$8,000

$18,000

F

Run pilot tests

C,D

5

2

$25,000

$34,000

1. What are the critical path and the estimated completion time?

2. To shorten the project by two weeks, which tasks would be shortened and what would the final total project cost be?

Process and Little's Law

Q3. Patients at Hoosiers Dental complained that the waiting time was too long and the dentist has asked you to investigate the problem. Based on conversation with staff members at the clinic, you have collected the information about the process. The service process includes four activities that are conducted in the sequence described below (the time required for each activity is shown in parentheses):

  • Activity 1: Fill out the paperwork (5 mins)
  • Activity 2: Enter patient information into the system (5 mins)
  • Activity 3: Take an X-ray (15 mins)
  • Activity 4: dental checkup (30 mins)

a. Which activity is the bottleneck?

b. What is the capacity of the entire process?

c. Assuming unlimited demand, what is the flow rate of the entire process?

d. What is the utilization rate of the employee at activity 3?

Q4. AutoDesk has 30 employees who work at its online customer service chat room. It receives, on average, 240 request per hour and each session takes 5 minutes to complete. On average, how many chat sessions are active?

Break-even analysis

Q5. Pat Egan owns a firework store. The store's fixed costs are $24,000 a month, and each firework assortment costs about $8, on average. The average selling price for an assortment is $20.

a. What is the break-even point for Pat's firework store?

Suppose Pat decides to expand his business. After expansion, the new fixed expense will be $40,000 per month, but the average cost for an assortment will be reduced to $5 due to his larger purchase volume.

b. What is the new break-even point?

c. At what volume point is Pat indifferent to the two alternatives outlined above?

Service Process

Q6. A car wash has a single crew of workers. Cars arrive the car wash every 8 minutes, following a Poisson distribution. The car wash can wash one car every 6 minutes and service times are exponentially distributed. Based on these numbers, find the following:

a. The average number of cars waiting.

b. The average number of cars in the system.

c. The average time a car spends waiting.

d. The average time a car spends in the system.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92019111

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As