Project Management Exercise -

The Beta project team has started gathering the information necessary to develop the project network diagram - predecessor activities and durations in weeks. The results of their meeting are found in the following table.

Activity

Description

Duration

Predecessor

1

Define Scope

6

None

2

Define Customer Problems

3

1

3

Define data records and relationship

5

1

4

Mass Storage Requirements

5

2, 3

5

Consultant Needs Analysis

11

2, 3

6

Prepare Installation Network

3

4

7

Estimate Costs and Budgets

2

4

8

Design Section Point System

1

4, 5

9

Write Request Proposal

5

5

10

Compile Vendor List

2

5

11

Prepare MGMT Control System

5

6, 7

12

Prepare Comparison Report

5

9, 10

13

Compare System Philosophies

5

8, 12

14

Compare Total Installation

2

8, 12

15

Compare Cost of Support

3

12

16

Compare Customer Satisfaction Level

8

12

17

Assign Philosophies Points

1

13

18

Assign Installation Cost

1

14

19

Assign Support Cost

1

15

20

Assign Customer Satisfaction Points

1

16

21

Select Best System

2

11, 17, 18, 19, 20

22

Order System

1

21

The project team has requested that you create a network diagram for the project, identify the critical path, and determine if the project can be completed in 50 weeks.

You are to first do a "hand drawn" solution, and then use Microsoft Project to create network diagram again. Assumptions: Start date is October 3, 2016, one shift per day, no overtime, no weekends, and all traditional holidays to be observed.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91983592

Have any Question?


Related Questions in Project Management

1 what are some benefits and values of scheduling software

1) What are some benefits and values of scheduling software in a project schedule?

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

Mikes tees a relatively large company that prints t-shirts

Mike's Tees, a relatively large company that prints T-shirts, is developing a system that allows customers to upload their image files on a server and have them printed on T-shirts. The project was drafted and planned to ...

The hospitality industry comprises diverse and varied

The hospitality industry comprises diverse and varied functions and scale of operations. Some organisations may be single function business enterprise such as catering organisation. Others may be larger with multiple bus ...

Assignment 1 the core values and principlesplease have the

Assignment 1: The Core Values and Principles Please have the following titles and include content as per assignment instructions under each paragraph: History of Agile project management. Philosophy and purpose of Agile ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessment descriptionyou are required to read a case study

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. Case Study - DeGrand ...

Advanced topics in project management assignment -outline -

Advanced Topics in Project Management Assignment - Outline - Project management is a highly regarded discipline in engineering. It experienced a number of changes or "natural evolution" in the last century, influenced by ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As