Project Management Assignment

Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.


Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100


Task B

4,000

Yes

Yes

4,500


Task C

2,500

Yes

Yes

2,250


Task D

4,000

Yes

No

3,500


Task E

3,500

Yes

Yes

4,000


Task F

2,500

No

No

0


1) Using the 50-50 Rule, what is earned value for this project?

2) Using the 0-100 Rule, what is earned value for this project?

3) Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.

4) Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?

5) What is the schedule performance index (SPI)?

6) Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?

7) What is the cost performance index (CPI)?

8) If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).

9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92078336
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Project Management

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

Part -1 define project and develop planperformance

Part -1 Define project and develop plan Performance objective Candidates will demonstrate knowledge and skills required to define projects and develop project plans. Assessment description Using the workplace scenario in ...

Check all of the following that arenbsptrue for top-down

Check all of the following that are  true for top-down estimates (when being compared with bottom-up estimates). Make sure your answer reflects what is correct for  Top-Down Estimates .  Lower cost to create estimate Hig ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

What are the types of documents required to define

What are the types of documents required to define parameters in a project?

Define the kano model and how it helps in gathering

Define the Kano model and how it helps in gathering customer requirements.

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As