Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Project Management Expert

Project Management Assignment

1) The following table shows the allocation of work assignments and resources needed for an investment firm to make a decision on investing in company XYZ.

 

Task A

Task B

Task C

Prtfolio Managers

Week 1 (S)

-

Week 3 (P)

Associates

-

Week 1 (P)

Week 2 (S)

Analysts

Week 1 (P)

Week 2 (P)

Week 2 (S)

(P)=Primary (S)=Secondary

Resource

Week 1

Week 2

Week 3

Prtfolio Manager

1

 

1

Associate

1

2

 

Analyst

2

5

 

Note: figures in spreadsheet are person-weeks of effort

a) Create Responsibility Matrix
b) Create Resource Gantt Chart
c) Create Resources Loading Chart

2) Building a swimming pool

 Task

Worker Category

Person Days

# of Workers

Elapsed Time (days)

Materials ($)

Excavate

Machine Operator

6

2

0

 1,500.00

Frame the walls

Masons

8

4

0

 800.00

Install Internal Plumbing

Plumber

4

2

0

 700.00

Install Electricity

Electrician

2

2

0

 500.00

Pour concrete

Masons

4

2

4

 2,000,00

Install pump and filter

Plumber

1

1

0

 3,000.00





Total

 8,500.00

 

Category

Wage Rate $/Day

Electrician

200.00

Mason

160.00

Machine operator

120.00

Plumber

200.00

a) Create a Gantt chart from the work breakdown structure.

b) Create a PERT/CPM network showing the interdependencies of the different activities. How long will the project take? (Note: Don't forget to take "elapsed time" into account.)

c) Using the information in your Gantt chart, as well as the information on wage rates and cost of materials, put together a budget showing planned total expenditures for the project.

3) Following are cost and schedule data for a project that is underway.

Project Cost Data

Month

Planned

Actual

1

30

12

2

35

23

3

42

55

4

46

55

5

40

53

6

52

60

7

45

75

8

48

80

9

50

 

10

40

 

11

30

 

12

15

 

Projects Schedule Date

Task

Planned Starting Month

Planned Duration (months)

Actual starting month

Actual Duration (months)

A

1

2

2

3

B

2

3

3

5

C

4

3

6

3   so far

D

6

5

7

2 so far

E

8

4

Not yet begun

 

F

10

3

Not yet begun

 

a) Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs.

b) Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance.

c) Summarize in words what you see project status to be at this time. What do you predict regarding the final cost and final schedule for the project?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92080188

Have any Question?


Related Questions in Project Management

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Define the kano model and how it helps in gathering

Define the Kano model and how it helps in gathering customer requirements.

Leading lean projects assessment case study - continuous

Leading Lean Projects Assessment Case study - Continuous Improvement Introduction - Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the t ...

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

Reflect on kotters 2007 steps for establishing a strategic

Reflect on Kotter's (2007) steps for establishing a strategic vision and buy-in for change. Describe how that framework can be applied to your strategic initiatives withinproject. Provide thoughts on how this could impro ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

What are the types of documents required to define

What are the types of documents required to define parameters in a project?

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

What is fast tracking and its impact on the project as it

What is fast tracking and its impact on the project as it relates to project management

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As