Project Management Assignment -

Introduction - All of you have had at least an introduction to earned value management in the project management fundamentals course. Many of you may have had the opportunity to use earned value management in your professional careers. In practice, most EVM analysis results are generated by scheduling software or other applications. As a project manager, you must have a good handle on the concepts and be able to verify the accuracy of EVM analysis results.

In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL ANALYSIS - DO NOT USE MICROSOFT PROJECT.

Problem Background - Your project consists of seven activities with planned start and finish dates shown in the chart below:

1603_figure.png

Activity budgets and earned value (EV) accrual rules from you project cost management plan are as follows:

Activity

Budget

EV Accrual Rule

1

25,000

Percent Complete with Gates

2

20,000

Fixed Formula - 0/100

3

50,000

Weighted Milestones

4

60,000

Percent Compete with Gates

5

30,000

Fixed Formula - 40/60

6

20,000

Fixed Formula - 30/70

7

10,000

Fixed Formula - 100/0

Assumptions -

1. Assume a five-day work week with no holidays occurring during the work week.

2. For all activities (except activities 3 and 4), assume the expenditure rate is constant over the duration of the activity, i.e., the amount planned to be spent each week is the same. See the conceptual profile below.

1081_figure1.png

3. For activity 3, the planned expenditure profile is shown below:

744_figure2.png

4. For activity 4, the planned expenditure profile is shown below:

1453_figure3.png

The project sponsor wants you (the PM) to present a project cost and schedule performance assessment using data through the end of week 8. You have collected the following information:

Activity

Actual Start

Actual Finish

Expended

1

Start of week 1

End of week 5

22,000

2

Start of week 6

End of week 8

25,000

3

Start of week 3

 

40,000

4

Start of week 8

 

8,000

5

 

 

0

6

 

 

0

7

 

 

0

For activity 1, three equally-valued gates have been established and all gates are complete as of the end of week 8.

For activity 3, five milestones have been established with the following values: (1) milestone 1 - 10%; milestone - 20%; milestone 3 - 15%; milestone 4 -20%; milestone 5 - 35%. Four of the milestones are complete as of the end of week 8.

For activity 4, four equally values gates (milestones) have been established. As of the end of week 8, none of the gates have been reached but the activity owner estimates 30% of the work required to reach the first gate has been accomplished.

1. Earned Value Measures

a. Calculate earned value measures for each activity and for the cumulative project as of the end of week 8;

2. Earned Value Performance Measures

a. Calculate earned value performance parameters for each activity and for the cumulative project as of the end of week 8;

b. Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why?

c. Is the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why?

3. Earned Value Forecasts

a. What is the value of the "Cumulative CPI" Estimate-at-Completion (EAC)?

b. Using the "Mathematical" or "Overrun to Date" Estimate-at Completion, what is the value of the Estimate-to-Complete (ETC)?

c. Using the "Cumulative CPI times SPI" Estimate-At-Completion, how much more or less money (other than the current budgeted amount) will you need to finish the project?

d. How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget?

Attachment:- Assignment File.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92728184
  • Price:- $55

Guranteed 36 Hours Delivery, In Price:- $55

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As