Project Management Assignment -

Introduction - All of you have had at least an introduction to earned value management in the project management fundamentals course. Many of you may have had the opportunity to use earned value management in your professional careers. In practice, most EVM analysis results are generated by scheduling software or other applications. As a project manager, you must have a good handle on the concepts and be able to verify the accuracy of EVM analysis results.

In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL ANALYSIS - DO NOT USE MICROSOFT PROJECT.

Problem Background - Your project consists of seven activities with planned start and finish dates shown in the chart below:

1603_figure.png

Activity budgets and earned value (EV) accrual rules from you project cost management plan are as follows:

Activity

Budget

EV Accrual Rule

1

25,000

Percent Complete with Gates

2

20,000

Fixed Formula - 0/100

3

50,000

Weighted Milestones

4

60,000

Percent Compete with Gates

5

30,000

Fixed Formula - 40/60

6

20,000

Fixed Formula - 30/70

7

10,000

Fixed Formula - 100/0

Assumptions -

1. Assume a five-day work week with no holidays occurring during the work week.

2. For all activities (except activities 3 and 4), assume the expenditure rate is constant over the duration of the activity, i.e., the amount planned to be spent each week is the same. See the conceptual profile below.

1081_figure1.png

3. For activity 3, the planned expenditure profile is shown below:

744_figure2.png

4. For activity 4, the planned expenditure profile is shown below:

1453_figure3.png

The project sponsor wants you (the PM) to present a project cost and schedule performance assessment using data through the end of week 8. You have collected the following information:

Activity

Actual Start

Actual Finish

Expended

1

Start of week 1

End of week 5

22,000

2

Start of week 6

End of week 8

25,000

3

Start of week 3

 

40,000

4

Start of week 8

 

8,000

5

 

 

0

6

 

 

0

7

 

 

0

For activity 1, three equally-valued gates have been established and all gates are complete as of the end of week 8.

For activity 3, five milestones have been established with the following values: (1) milestone 1 - 10%; milestone - 20%; milestone 3 - 15%; milestone 4 -20%; milestone 5 - 35%. Four of the milestones are complete as of the end of week 8.

For activity 4, four equally values gates (milestones) have been established. As of the end of week 8, none of the gates have been reached but the activity owner estimates 30% of the work required to reach the first gate has been accomplished.

1. Earned Value Measures

a. Calculate earned value measures for each activity and for the cumulative project as of the end of week 8;

2. Earned Value Performance Measures

a. Calculate earned value performance parameters for each activity and for the cumulative project as of the end of week 8;

b. Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why?

c. Is the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why?

3. Earned Value Forecasts

a. What is the value of the "Cumulative CPI" Estimate-at-Completion (EAC)?

b. Using the "Mathematical" or "Overrun to Date" Estimate-at Completion, what is the value of the Estimate-to-Complete (ETC)?

c. Using the "Cumulative CPI times SPI" Estimate-At-Completion, how much more or less money (other than the current budgeted amount) will you need to finish the project?

d. How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget?

Attachment:- Assignment File.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92728184
  • Price:- $55

Guranteed 36 Hours Delivery, In Price:- $55

Have any Question?


Related Questions in Project Management

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

How might researchers study the effectiveness of inclusive

How might researchers study the effectiveness of inclusive leadership with regard to overall organizational effectiveness and competitiveness?

1 what are some benefits and values of scheduling software

1) What are some benefits and values of scheduling software in a project schedule?

The hospitality industry comprises diverse and varied

The hospitality industry comprises diverse and varied functions and scale of operations. Some organisations may be single function business enterprise such as catering organisation. Others may be larger with multiple bus ...

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

How does developing interpersonal skills enhance individual

How does developing interpersonal skills enhance individual and team performance

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Assessment descriptionyou are required to read a case study

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. Case Study - DeGrand ...

You are recently assigned to manage an effort to upgrade

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your compan ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As