1. What is the purpose of the project?
2. Who tasked it and who sponsors it (you should hypothesize a sensible choice of sponsor at Acme headquarters in NC, USA)
3. Why it was tasked (= business need or goal)
Given the case is : "Background Information for Acme Mexico City".
Assignment
Acme de México has purchased a site on which it intends to build and open a new store in Mexico City [Acme Mexico City (AMC)]. The store will have the Acme average 100,000 square feet of indoor space and 10,000 square feet of exterior space for garden products.
In addition, a two-story parking garage will be built directly adjacent to the store. It is desired that the project should take no longer than 12 months. The store construction and opening processes include at least eight major activities. Hint: one necessary major activity is omitted; which is it?
THINK CRITICALLY
1. Obtain required licenses and permits.
2. Prepare the site and lay the foundation.
3. Build the walls, floor, and roof of the structure.
4. Install electrical and plumbing fixtures.
5. Finish interior and stock inventory.
6. Build the garage.
7. Complete all paving and landscaping.
8. Hire and train employees
Attachment:- Assignment-Instructions-.rar