Problem 1:

You have been asked to determine a schedule for a nine month Billing System project as part of your job as a consultant to a Fortune 500 firm. The firm's old system was written in COBOL on a mainframe computer, and the maintenance costs are prohibitive. The new systems will run on an off-the-shelf application. You have identified several high level tasks needed to initiate, plan, execute, control, and close the project. Table 6-4 below shows your analysis of the projects tasks so far.

a.) Using the information in Table 6-4, draw horizontal bars to illustrate when you think each task would logically start and end. In addition, identify task dependencies for inclusion in part b.) and at least 2 milestones for each of the five process groups in table 6-4 also for inclusion in part b.). For part a.), I want to see your work (notes, sketches, lists, drawings, etc.) that you generated. (This can all be hand drawn and scanned)

b.) Create a Gantt chart using the tasks, durations, dependencies, and milestones from part a.). The Gantt chart should include proper formatting to show summary tasks, individual tasks (dependent and independent), and milestones. For part b.), your formatted Gantt chart can be hand drawn and scanned or you can use a software package.

TABLE COBOL conversion project schedule








Tasks Mar Apr May Jun Jul Aug Sep Oct Nov
Initiating








Develop project charter








Meet with stakeholders








Planning








Create detailed WBS and schedule








Estimate project costs








Create project team








Create communication plan








Organize a comprehensive project plan








Executing








Award and manage contract for software conversion








Install new software on servers








Install new hardware and software on clients' machines








Test new billing system








Train users on new system








Controlling 








Closing








Problem 2:

Write an essay describing the overall purpose and benefits of project scope management. Include a detailed description of all of the main processes involved in project scope management and the relationship they have to each other. Explain why each one is used and what the negative impact would be to the overall project if one or more were ignored. Your response in essay format should be no less than 2 pages long.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91703038

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As