Problem 1: Given the information provided below (predecessors, normal time, normal cost, crash time (the minimum duration) and crash cost (the cost if crashed to the minimum duration) for an nine-activity (a to i) project) answer the questions (a) through (e) using this template.

Activity

Predecessor

Normal Time

Normal Cost

Crash Time

Crash Cost

a

-

4

 $ 50

2

 $ 150

b

a

4

 $ 40

2

 $ 200

c

b

7

 $ 70

4

 $ 160

d

c, f

2

 $ 20

1

 $ 50

e

c

3

 $ 30

2

 $ 100

f

b

8

 $ 80

5

 $ 290

g

d, e

5

 $ 50

3

 $ 100

h

f

6

 $ 60

2

 $ 180

i

g, h

3

 $ 50

3

$ 50

(a). Create the network diagram in the application of your choice and then insert a screen shot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function.

Identify the critical path of the network, the time, and cost of the normal level of activity for the project:

• The critical path (or paths) is: __________________
• The project duration: ___________
• The project cost is: _____________

(b). Calculate the crash cost-per-day (all activities may be partially crashed). Enter your response to question 1(b) in the table provided below

Activity

Normal Time

Normal Cost

Crash Time

Crash Cost

Crash Cost/Day

a

 

 

 

 

 

b

 

 

 

 

 

c

 

 

 

 

 

d

 

 

 

 

 

e

 

 

 

 

 

f

 

 

 

 

 

g

 

 

 

 

 

h

 

 

 

 

 

i

 

 

 

 

 

(c). Find the optimal way to crash the project by one day.

• What is the projected project cost?
• What is the projected project duration?
• What is the critical path (or paths)?
• What task or tasks were crashed?

Explain the results of your calculations.

(d). Find the optimal way to crash the project by two days.

• What is the projected project cost?
• What is the projected project duration?
• What is the critical path (or paths)?
• What task or tasks were crashed?

Explain the results of your calculations.

(e). Calculate the shortest completion time for the project.

• What is the projected project cost?
• What is the projected project duration?
• What is the critical path (or paths)?
• What task or tasks were crashed?

Explain the results of your calculations.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92039250

Have any Question?


Related Questions in Project Management

What are the types of documents required to define

What are the types of documents required to define parameters in a project?

42908 assessment task - project proposal1 executive summary

42908 Assessment Task - Project Proposal 1. Executive Summary - Brief overview of project, main aim of project, potential findings and conclusions. 2. Introduction - Presents general project area, relevance of project, s ...

Define the kano model and how it helps in gathering

Define the Kano model and how it helps in gathering customer requirements.

How does developing interpersonal skills enhance individual

How does developing interpersonal skills enhance individual and team performance

The hospitality industry comprises diverse and varied

The hospitality industry comprises diverse and varied functions and scale of operations. Some organisations may be single function business enterprise such as catering organisation. Others may be larger with multiple bus ...

As a project manager answer these questions1 a how does the

As a project manager answer these questions, 1) a. How does the weighted scoring approach avoid the drawbacks of the NPV approach? b. Can the two approaches be combined? if so How? How are you going to apply this piece o ...

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

Project proposal -project - plan for implementing spc for

PROJECT PROPOSAL - Project - Plan for implementing SPC for improvement Introduction/aims/objectives - 200 words max Indicative literature review - 500 words max Indicative research methodology - 500 words max An idea to ...

What are the advantages and disadvantages of cost of poor

What are the advantages and disadvantages of Cost of Poor Quality (COPQ)?

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As