Perform a financial analysis for a project using the format. Assume the costs and benefits for this project are spread over four years as follows.

Estimated costs are $155,000 in Year 1 and $5,000 each year in Years 2, 3 and 4. The discount factors will automatically be recalculated. Estimated benefits are $0 in Year 1 and $42,000 each year in Years 2, 3 and 4.

Use a 12% discount rate (interest rate). Use given template to calculate NPV and ROI, and year in which payback occurs.

Show your work by attaching the completed template and write a paragraph explaining whether you would recommend investing in this project based on your financial analysis.

AN INTRODUCTION TO PROJECT MANAGEMENT, FOURTH EDITION

Figure. Intranet project NPV example (Schwalbe, Information Technology Project Management, Sixth Edition, 2010)

Discount rate

4%

 

 

 

 

 

 

1

2

3

4

Total

 

Costs

150,000

5,000

5,000

4,000

 

 

Discount factor

0.96

0.92

0.89

0.85

 

 

Discounted costs

144,230.769

4,622.781

4,444.982

3,419.217

156,717.749

 

 

 

 

 

 

 

 

Benefits

0

80,000

80,000

80,000

 

 

Discount factor

0.96

0.92

0.89

0.85

 

 

Discounted benefits

0

73,964.497

71,119.709

68,384.335

213,468.541

4

 

 

 

 

 

 

 

 

Discounted benefits - costs

-144,230.769

69,341.716

66,674.727

64/965.119

56,750.792

NPV

Cumulative benefits - costs       

-144,230.769

-74,889.053

-8,214.326

50750.792

 

 

 

 

 

 

 

 

 

ROI

0.362121027

 

 

 

 

 

 

 

 

 

Payback In Year 4

To determine NPV, follow these steps:

1. Determine the estimated costs and benefits for the life of the project and the products it produces. For example, the intranet project example assumed the project would produce a system in about six months that would be used for three years, so costs are included in Year o, when the system is developed, and ongoing system costs and projected benefits are included for Years 1, 2, and 3.

2. Determine the discount rate. A discount rate is the rate used in discounting future cash flows. It is also called the capitalization rate or opportunity cost of capital. In Figures 2-3 and 2-4, the discount rate is 10% per year, and in Figure 2-5, the discount rate is 8% per year.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91615253
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Project Management

Mikes tees a relatively large company that prints t-shirts

Mike's Tees, a relatively large company that prints T-shirts, is developing a system that allows customers to upload their image files on a server and have them printed on T-shirts. The project was drafted and planned to ...

You are recently assigned to manage an effort to upgrade

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your compan ...

Assignment 1 the core values and principlesplease have the

Assignment 1: The Core Values and Principles Please have the following titles and include content as per assignment instructions under each paragraph: History of Agile project management. Philosophy and purpose of Agile ...

What is fast tracking and its impact on the project as it

What is fast tracking and its impact on the project as it relates to project management

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Assessment descriptionyou are required to read a case study

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. Case Study - DeGrand ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Assessment descriptionyou are required to read a case

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. The case study will ...

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As